ML20071M084

From kanterella
Jump to navigation Jump to search
Forwards Monthly Operating Rept for Jul 1982
ML20071M084
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 08/26/1982
From: Murray T
TOLEDO EDISON CO.
To: Haller N
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
Shared Package
ML20071M086 List:
References
K82-1231, NUDOCS 8209240248
Download: ML20071M084 (1)


Text

_

,e TOLEDO

%ms EDISON August 26, 1982 Log No. K82-1231 FILE: RR 2 P-6 (P-6-82-07)

Docket No. 50-346 License No. NPF-3 Mr. Norman Italler, Director Office of Inspection and Program Analysis U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Dear Mr. Italler:

Enclosed are ten copies of Revision 1 to the Monthly Operating Report for Davis-Besse Nuclear Power Station Unit I for the month of July, 1982. The revision to the report is indicated by a "1" in the left margin of each page.

Please replace your previous copies of this report with the attached revision.

Yours truly, Terry D. Murray Station Superintendent Davis-Besse Nuclear Power Station TDM/BMS/1mr Enclosure cc:

Mr. James G. Keppler Regional Administrator, Region III Encl:

I copy Mr. Richard DeYoung, Director Office of Inspection and Enforcement Enc 1:

2 copies Mr. Walt Rogers NRC Resident Inspector Encl:

1 copy 8209240248 020026 I

PDR ADOCK 05000346 R

PDR THE TOLEDO ED! SON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO. OHIO 43652

...