Site: Hatch  Southern Nuclear icon.png
Issue date: 04/16/1982
From: Beckham J
GEORGIA POWER CO.
To:
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737 GL-82-05, GL-82-5, NUDOCS 8204270428
Download: ML20071J986 (1)


Text

Geu'; a Power Ccm pan, 311 P.omnt /c.enue ANnta Georg a 30308 Tc:" phone 404 b.?6 7020 Maing Arftsc ss f'o,t O't.cc Bo s 4 545 b

A':anta Georg a 30302 GeorgiaPower I

"I"" "I'* W' J. T. Beckham, Jr.

Oce Presvient anct Genera! f.*rager nua.w c.ncranen April 16, 1982

-~

6 q

\\

G rec 5;ygg Director of Nuclear Reactor Regulation 2

72 U. S. Nuclear Regulatory Commission 8. amApg20 ISO 2h seier d p Washington, D. C.

20555 k

NRC DOCKETS 50-321, 50-366 02 OPERATING LICENSES DPR-57, NPF-5 EDWIN I. HATCH NUCLEAR PLANTS UNITS 1, 2 POST TMI REQUIREMENTS IMPLEMENTATION SCHEDULE INFORMATION Gentlemen:

Your letter of March 17, 1982, (Generic letter number 82-05) requested by April 16, 1982, confirmation of completion or a schedule for completion for a number of requirements promulgated by NUREG-0737 We have been unable to comply with the requested submittal date due to the level of activity presently required to support the refuelling outage currently under way on Unit 2.

The requested information will be submitted by April 20, 1982. We regret any inconvenience this delay may have caused.

Yours very truly,

. O f