Urges Denial of Util Request to Extend CP Expiration Date. Suffolk County Determination That Evacuation Is Impossible Disposes of OL Question
ML20071F487
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 04/06/1983
From: Brannen J, Runco F, Van Kovics J
SAG HARBOR, NY
To: Harold Denton
Office of Nuclear Reactor Regulation
Shared Package
ML20071F484 List:
References
NUDOCS 8305180461
Download: ML20071F487 (3)


Text

i.

tN.55 6-OF SKG y ns pp'cw d.hW3

(

A G lSU S16 725 0222 P. O BOX 660 M AIN ST.. S AG H ARB OR. L. L. NEW YORK 11963 wagon FERDINAND RIJNCo TauSTEE5 JAMES BRANNEN PATRICK KERN EDWARD GREGORY JANE VAN KOVICS JOAN E. SCHOEN C AROL A. SCMROEDER CLEma e TREA5 DEPUTY clean April 6, 1983 Mr. Harold R. Denton Director Nuclear Reactor Regulation U.S.

Nuclear Regulatory Commission Washington, D.C.

20555 Re:

Shoreham Nuclear Power Station Construction Permit #CPPR-95

Dear Mr. Denton:

I am the Mayor of the Village of Sag Harbor on eastern Long Island, which lies East of LILCO's Shoreham Nuclear Power Plant.

The Village of Sag Harbor is home to more than 2800 year-round residents, l

and in the summer, our population swells to more than 5000 people.

l It has come to my attention that the construction permit for Shoreham is due to expire on March 31, 1983 unless extended by your office.

This letter is to urge you to deny LILCO's request to continue c6n-struction at Shoreham and to prevent _the further wasteful expenditure i

of tens of millions of dollars on that project.

As you know, Suffolk County has determined, on the basis of many months of intensive examination by experts, that the safe evacuation of Suffolk County residents, particularly those who reside in eastern Long Island, cannot be accomplished.

Accordingly, Suffolk County has urged the NRC to terminate the Shoreham operating license proceedings in view of the fact that approval and implementation of a suffolk County off-site emergency plan is a requirement for the issuance of an operating license.

I agree with the County's determination and can see no reason why your office should permit construction at Shoreham to continue.

l I have also been made aware of comments atrributable to NRC 8305180461 830517 i

PDR ADOCK 05000322 t m tow wr.c aci ir.cor.noa Arco m uuce ac me o

PDR

Mr. Harold R. D;nton

(

,,4pr,il 6, 1983

p PCga Two

+

cpokesmen in Long Island's daily newspaper, Nessday, which suggests that less than serious attention will be given to Suffolk County's request that construction at Shoreham be halted.

For example, James Fitzgerald, an assistant general counsel at the NRC, reportedly stated "I don't think you need an evacuation plan during the construction phase," while NRC spokesman Frank Ingram is alleged to have said "Re-quests to extend plant construction dates are a dime a dozen."

(See attached Newsday article.)

These comments do nothing to instill con-fidence in the integrity of the NRC decision-making process, and I trust that they are not indicative of the attention that you will de-vote to this matter.

It is my belief that the County's determination that there can be no safe evacuation of Suffolk County residents is dispositive of the question of whether Shoreham will be permitted to operate.

In view of that controlling fact, it would be irresponsible for your office to continue to permit LILCO to expend millions of dollars in funds for construction.

I strongly object to any action (or inaction) by the NRC that would permit Shoreham's cost to unnecessarily escalate even further.

I urge you to give Suffolk County's opposition to the extension of LILCO's construction permit your immediate and thoughtful attention.

I look forward to hearing your response to my c.oncern.

d

~

V t ul

ours, 4

g Fred Runco, Mayor cm bn e ames Br nnen, T stge

// s i f fr a lhW e Ja'ne Va"n ~K6vTcts, Trustee hah;Alek~

P'a t r i c k K'e r b, Trustee a t o,4MA e Edward Gregcity, (Trustee FR/cs

Enclosures:

Newsday article cc:

Chariman Palladino Commissicners Martin Lang, Supervisor Town of Southampton

i C

.p..

=

S 2 /s er r nd it, 1

t REGIDX Permit Extension For N-Plant Fought By Robert Fresco in an unusual move aimed at preventing the opening of the Shoreham nuclear plant, Suffolk County has asked the federal Nuclear Regulatory Comminaion to block a routine er,ension of the plant's construction permit.

The county contends in its request that because it has not approved an emergency evacuation plan for the plant, Shoreham cannot open, and as a re-sult, construction should not proceed.

But the legality of the county action was imme-diately questioned by a top NRC attorney. James Fitzgerald, an assistant general counsel, said he doubted the county's cbjection had any legal hasis. "i don't think you need an evacuation plan during the construction phase," he said.

And NRC spokesman Frank Ingram said that

  • requests to extend plant construction dates are a dime a dozen." And, he added, the commission rou-tinely grants them.

"His attitude doesn't surprise me," Deputy r

County Executive Frank Jones said of Fitzgerald's i

comment. "The Nuclear Regulatory Commission consistently falls on the side of the nuclear-power advocates."

.l.1140*: construction permit expires March 31.

On Feb. 25, the company submitted a request for a l

nine-month extension. IJILO spokeswornan Judith Brabham s. aid that the utility is not changing ita I

presious!y announced plan to load fuel into the reae.

tor by the end ofJune and begin comrnercial produe-l tion of electric power there in early 1984. She said an extension beyond June was requested to allow

" minor construction work" such as painting in the "non-nuclear" area of the plant.

i L1140's construction permit for the $3.2-billion plant has already been extended twice, Brabham said. The original permit was grated in April, 1973, and expired in Wy,1979. Brabham said it was

  • customary" for utilities to ask for extensions.

But the county's lawyer, Herbert Brown, wrote I

in a letter Wednesday to the NRC,"We submit that l

the IJLCO request (for the ertension) can't lawfully be granted." This, he argued,is because,"no operat-ing license for the Shoreham plant can lawfully be l

issued," since there is no emergency evacuation plan for the plant. "SufTolk County has resolved that it will not adopt or implement" such a plan, he added.

i

.