,y

[~ *s Commonwealth Edison

) One First Nitional Pttra, Chic 3go, lihnois g

' ^ ~ ' '

(

Addrzss Riply to: Post Offics Box 767 y

Chicago, Illinois 60690 March 8, 1983 Mr. Harold R. Denton, Director Of fice of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Byron Station Units 1 and 2 Pre-Fire Plans NRC Docket Nos. 50-454 and 50-455 References (a):

Branch Technical Position CMEB 9.5-1 Position C.l.E.

(b):

10 CFR 50, Appendix R, Section 3.K.12.

Dear Mr. Denton:

Reference (a) requires that the fire protection program be implemented for the building in which new fuel is going to be stored.

Reference (b) requires that strategies be developed for fighting fires.

The purpose of this letter is to inform you that the Byron Station Pre-Fire Plans have been developed for the areas that are necessary for the receipt of new fuel.

These pre-fire plans are available on-site for review by the NRC.

By copy of this letter, Mr. James G. Keppler, Regional Administrator is also informed of the status of these plans.

Enclosed please find one (1) signed original and forty (40) copies of this letter.

If there are any questions in this matter, please contact this office.

Very truly yours, 3/s/s3 C.

W. Schroeder Nuclear Licensing Administrator 1m cc:

Mr.

J. G. Keppler - RIII Mr. Chuck Ramsey - RIII RIII Inspector - Byron Station 8303150326 830308 PDR ADOCK 05000454 F

PDR 6152N