Informs That Final Deficiency Rept Scd 42 Re Hma Auxiliary Relays Reopened.Caused by Inadequate Reflection of Scope of Corrective Action.Final Rept Expected by 830328
ML20071B701
Person / Time
Site: Waterford Entergy icon.png
Issue date: 02/14/1983
From: Maurin L
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, SCD-42, W3I83-0049, W3I83-49, NUDOCS 8302280535
Download: ML20071B701 (1)


Text

LOUISIANA m u aAnaNoe Srneer P O W E R & ~ L I G H T[ R o. Box 6008

  • NEW ORLEANS. LOUISIANA * (504) 366-2345 70174

!$uS$s*fsSE February 14, 1983 L v. uAunin Voce President Nuclear Operations W3183-0049 Q-3-A35.07.42 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission t h

& @ % - {c. s ,

~q 611 Ryan Plaza Drive, Suite 1000 l'J/i Arlington,~ Texas 76012 if 822m (l 7

SUBJECT:

Waterford SES Unit No. 3 Docket No. 50-382 L ' "-

Significant Construction Deficiency No. 42 _

"HMA Auxiliary Relays"

REFERENCE:

LP&L letter W3183-0017 dated January 24, 1983

Dear Mr. Collins:

The ateve referenced letter reopened SCD 42 because the scope of the correct ive action was not adequately reflected in the final report. Verification of the corrective action and review of documentation is still ongoing. It is anticipated that this effort will be completed and a final report submitted by March 28, 1983.

Very truly yours, f hukN L. V. Maurin LVM/ MAL:keh cc: 1) Director 3) E. L. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555

2) Director 4) W. M. Stevenson l Office of Management l Information and Program Control U. S. Nuclear Regulatory Commission Washington, D. C. 20555 y

1 l

r302280535 830214 PDR ADOCK 05000382 PDR S