Text
\\
if a
}
NL _
THE CINCINNATI GAS & ELECTRIC COMPANY aN CINCINNATl. OHIO 452ol August 6, 1982 QA-1918 s
L A. BORG MAN N SEMOR VICE PRESIDENT U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 Attention:
Mr. J. G. Keppler Regional Administrator RE:
WM. H. ZIMMER NUCLEAR POWER STATION UNIT I I.E. INSPECTION REPORT NO. 80-25, CG&E S.W.O. #80 DOCKET NO. 50-358, CONSTRUCTION PERMIT NO. CPPR-88, W.O. #57300 JOB E-5590 FILE NO. NRC-1 Centlemen:
In accordance with CG&E Letter QA-1405 and discussions between Mr. H. Sager - CG&E QA and Mr. D. Danielson - NRC Region III on 8-5-82, the Cincinnati Gas & Electric Co. requests concurrence with a partial release of Stop Work Order 80-14.
This partial release would be limited to the removal of hangers / supports, installed by Reactor Controls Inc., which are no longer acceptable from a design stand point based on the Sargent & Lundy design analysis to support redefined systems loads.
This partial release would facilitate the construction schedule and has no impact on determining the acceptability of work performed by Reactor Controls Inc.
If any additional infermation regarding the above is required, please contact Mr. H. R. Sager.
Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY By
'g" '
E. A. BORGMANN SENIOR VICE PRESIDENT CWV:as l
cc:
NRC Office of Inspection & Enforcement Washington, D.C.
20555 NRC Senior Resident Inspector Attn:
W. F. Christianson Zimmer Project Inspector Region III 1~-
8302040432 820806 PDR ADOCK 05000358 AUG 11 1982 O