Text
.-
,/
Ccmm:nwealth Ediscn 1400 opus Place i _ 7 Downers Grove, Illinois 60515
'M (V
March 4,1991 Mr. A. Bert Davis Regional Administrator U.S. Nuclear Regulatory Commission 799 Roosevelt Road Rill Glen Ellyn,il 60137
Subject:
Byron Station Unit 2 Cycle 3 Star 1u a Report NRC DocketFosJ0-455
Dear Mr. Davis:
Section 6.9.1 of the Byron Technical Specification states, in addition to the applicable reporting requirements of Title 10, Code of Federal Regulations, the fol.owing reports shall be submitted to the Regional Administralor of the NRC Regional Office unless otherwise noted:
6.9.1.1. A summary report of plant startup and power escalation testing shall be submitted following: (1) receipt of an Operating License, (2) amendment to the license involving a planned Increase in power level, (3) Installation of fuel that has a different design or hm been manuiactured by a different fuel
' supplier, and (4) modifications that may have significantly altered the nuclear, thermal, or hydraulic performance of the plant.
6.9.1.2. The Startua Report shall address each of the tests identitled in the Final Safety Analys s Report FSAR and shallinclude a description of the measured values of the operating conditions or characteristics obtained during the test program and a comparison of these values with design predictions and specifications. Any corrective actions that were required to obtain satisfactory operation shall also be described. Any additional specific details required in license conditions based on other commitments shall be included in this report.
6.9.1.3. Startup Reports shall be submitted within: (1) 90 days following completion of the Startup Test Program. (2) 90 days following resumption or commencement of commercial power operation. or (3) 9 months following initial criticality, whichever is earliest. If the Startup Report does not cover all three events (i.e., initial criticality, completion of Startup Test Program, and resumption or commencement of commercial operation) supplementary reports shall be submitted at least every 3 months until all three events have been completed.
910312O333 91030A PDR ADOCK 05000455 PDR i
1] { {j d
\\
A. Bert Davis 2-March 4,1997 l
in accordance with Specification 6.9.1.1(3) and 6.9.1.3(1), enclosed is the Byron Unit 2, Cycle 3 Startup Report.
Please address any questions regarding this submittal to this office.
Sincerely, fL(<stl Y l
W Y
Terence K. Schuster
-I Nuclear Licensing Administrator NRC bocumen~t Chntrol' Desk cc: