Interim Significant Const Deficiency Rept 49 Re Time-Trol, Inc Heat Trace Panel Malfunctions.Defective Modules Still Being Replaced.Final Rept to Be Submitted by 830118
ML20070F729
Person / Time
Site: Waterford Entergy icon.png
Issue date: 11/30/1982
From: Maurin L
LOUISIANA POWER & LIGHT CO.
To: Jay Collins
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
10CFR-050.55E, 10CFR-50.55E, W3I82-0120, W3I82-120, NUDOCS 8212210230
Download: ML20070F729 (1)


Text

I OUISIANA f 242 OetinONoe s1nter POWE R & LIG HT/ P O BOX 6008 = NEW ORLEANS. LOU:SIANA 70174 * (504) 366-2345

[$ EON s*fbSE November 30, 1982 L v uA vain Vice Presnient Nuclear Operatens W3I82-0120 Q-3-A35.07.49 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012

SUBJECT:

Waterford SES Unit No. 3 Docket No. 50-382 Significant Construction Deficiency No. 49

" Time-Trol Inc., Heat Trace Panel Malfunctions"

REFERENCE:

LP&L Letter W3K82-0465 to USNRC dated July 30, 1982

Dear Mr. Collins:

The above referenced letter indicated that a final report would be submitted by November 30, 1982.

At this time corrective action to replace defective modules is still I

in progress, therefore, we will be unable to submit the final report until January 18, 1983.

Very truly yours, g

[ b-

/

L. V. Maurin LVM/WAC:keh j

cc:

1) Director 3)

E. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555

2) Director 4)

W. Stevenson Office of Management Information and Program Control dL_&2[

U. S. Nuclear Regulatory Commission Washington, D. C.

20555 8212210230 821130 PDR ADOCK 05000382 S

PDR