LOU 1SIANA P O W E R & L i G H T! P O Box coos. NEW ORLEANS. LOUIStANA 70174 142 DRAAONDE STREET
. (504) 366 2345 u':N$ s5sM November 15, 1982 L. V MAURIN Voce President Nuclear Operations W3182-0095 Q-3-A35.07.40 Mr. John T. Collins, Regional Administrator, Region IV 1
U. S. Nuclear Regulatory Commission
%["d @ %"{ l\\\\l/(i 611 Ryan Plaza Drive, Suite 1000 lb J
+1 Arlington, Texas 76012
, ki ' NOV i 71982 J ("\\l l t h
SUBJECT:
Waterford SES Unit No. 3 l
Docket No. 50-382 Significant Construction Deficiency Report No. 40,
l "ITE - Gould Starter Coil Failure in Containment Cooling Fans" Seventh Interim Report
REFERENCES:
- 1) LP&L Letter W3K-81-0412 Dated November 17, 1982
- 2) LP&L Letter W3I82-0032 Dated September 15, 1982
Dear Mr. Collins:
The ITE-Gould Company received from Ebasco six (6) starter coils for examination and evaluation to determine why the coils failed. Part of the examination will be performed by an outside test lab. The lab testing is scheduled to be completed by December 10, 1982. When the test report is received, it will be evaluated and a final report submitted.
In view of the above, a final report will be submitted by January 10, 1983.
Very truly yours,
$)
derd L. V. Maurin LVM/ MAL:keh cc:
- 1) Director 3)
E. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission 4)
W. Stevenson Washington, D. C.
20555
- 2) Director Office of Management Information and Program Control h
\\(v, U. S. Nuclear Regulatory Commission Washington. n c.
20555 O212210172 021115 PDRADOCK05000g S