LOUISIANA f 24a OttAnoNOe srncer P O // E R & L 1 G H T/ P O. BOX 6008. NEW OnLEANS. LOUISlANA 70174. (504) 3S6-2345 un'OCL E SOUTH November 30, 1982 M
unts system L Y MAURIN sce Presxient Nuclear Operations W3182-0119 Q-3-A35.07.50 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012
SUBJECT:
Waterford SES Unit No. 3 Docket No. 50-382 Significant Construction Deficiency No. 50 "Possible Malfunction In Agastat E7000 Series Time-Delay Relays"
REFERENCE:
LP&L Letter W3K82-0421 to USNRC dated July 15, 1982
Dear Mr. Collins:
In the above referenced letter LP&L indicated that a final report would be issued on Significant Construction Deficiency No. 50 by November 30, 1982.
At the present time all corrective actions have been taken and documentation is being assembled by the contractor for Quality Assurance review, however, additional time is necessary to complete the QA review and prepare a final report.
Therefore, the final report will be submitted by January 5, 1983.
Very truly yours, rh L. V. Maurin j
LVM/WAC:keh cc:
- 1) Director 3)
E. Blake Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.
20555