Text
_ _ _ _ _ _ _
s Northem States Power Company 414 Nicollet Mall Minneapolis, Minnesota 55401-1927 Telephone (612) 330-5500 June 14, 1994 Monticello Technical Specifications Section 6.7.A.3 US Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 MONTICELLO NUCLEAR GENERATING PLANT Docket No. 50-263 License No. DPR-22 Monthly Operating Report May, 1994 Attached is the Monthly operating Report for May, 1994 for the Monticello Nuclear Generating Plant.
iffp' p
of Roger O Anders n Director Licensing and Management Issues c:
Director, Office of Resource Management Regional Administrator-III, NRC NRR Project Manager, NRC NRC Resident Inspector State of Minnesota - Kris Sanda Attachment i
9406220002 940531
/
PDR ADOCK 05000263
/.h 8
h.. t t,
PDR l
l i
f f
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50-263 UNIT Monticello-DATE 6-1-94 COMPLETED BY H.
H.
Paustian TELEPHONE G12/295-5151 MONTH OF MAY DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Met)
(MWe-Net) 1 547.
17 542.
2 547.
18 543.
3 547.
19 541.
4 546.
20 539.
5 547.
21 541.
6
- 545, 22 535.
7 549.
23 537.
8 544.
24 536.
9 545.
25 536.
10 546.
26 536.
11 547.
27 534.
12 542.
28 534.
13 544.
29 531.
14 545.
30 531.
15 540.
31 531.
16 545.
INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month.
Compute to the nearest whole megawatt.
OPERATING DATA REPORT
+
DOCKET NO.
50-263 DATE 6-1-94 COMPLETED BY H.
H.
Paustian TELEPHONE 612/295-5151 OPERATING STATUS
] Notes
]
- 1. Unit Name :
Monticello
]
]
2.
Reporting period:
MAY
]
]
- 3. Licensed Thermal Power (MWt):
1670
]
]
- 4. Nameplate Rating (Gross MWe) :
569
]
. ]
- 5. Design Electrical Rating (Net MWe) :
545.4
]
]
- 6. Maximum Dependable Capacity (Gross MWe) : __564
]
]
- 7. Maximum Dependable Capacity (Net MWe) :
536
]
]
8.
If Changes Occur in Capacity Ratings (Items Number 3_Through 7) Since Last Report, Give Reasons:
9.
Power Level To Which Restricted, If Any (Net MWe):
N/A i
- 10. Reasons For Restrictions, If Any: __N/A THIS MONTH YR.-TO-DATE CUMULATIVE 4
- 11. Hours In Reporting Period 744-3623 200901
- 12. Number Of Hours Reactor Was Critical 744.0 3580.5 162956.2 i
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 940.7 t
- 14. Hours Generator On-Line 744.0 3570.4 160171.1
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0 l
- 16. Gross Thermal Energy Generated (MWH) 1241544 5942258 247207038
- 17. Gross Electrical Energy Generated (MWH) 418749 2014697 83569360
- 18. Net Electrical Energy Generated (MNH) 402550 1941375 79960168
- 19. Unit Service Factor 100.0%
98.5%
79.7%
- 20. Unit Availability Factor 100.0%
98.5%
79.7%
- 21. Unit Capacity Factor (Using MDC Net) 100.9%
100.0%
74.3%
- 22. Unit Capacity Factor (Using DER Net) 99.2%
98.2%
73.0%
- 23. Unit Forced Outage Rate 0.0%
1.5%
3.6%
l
- 24. Shutdowns Scheduled Over Next 12 Months (Type, Date, and Duration of Each) j
- Refueling Outage - 9/15/94 - 39 days
$ 25. If Shut Down At End Of Report Period, Estimated Date Of Startup:N/A
- 26. Units In Test Status (Prior to Commercial Operation) : N/A Forecast Achieved INITIAL CRITICALITY
)
INITIAL ELECTRICITY COMMERCIAL OPERATION
.f 6
G Ns i
a m-
.-,..r e-r em-revi,.-ev
NARRATIVE
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.
50-263 DATE 6-1-94 COMPLETED BY H. H.
Paustian I
TELEPHONE 612/295-5151 MONTH MAY l
05-1-94 to Power operation.
05-31-94 l
1 i
i l
i Note: Power operation defined as essentially 100% of rated power except for weekend load drops for specified surveillance testing.
~
i UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.
50-263 UNIT NAME -Monticello DATE 01-94 COMPLETED BY -H. H. Paustran REPORT MONTH May TELEPHONE 2612/295-5151 ~
}
Duration Reason Method LER System Comp.
Cause & Corrective No.
Date Ty(pe (hours)
(2) of No.
Code Code Action to 1) 4 Shutdown (4)
(5)
Prevent Recurrence (3) h None a
J
\\
l 4
i I
t 1
2 3
4 F: Forced Reason:
Method:
Draft IEEE Standard S: Scheduled A-Equipment Failure (Explain) 1-Manual 805-1984(P805-DS) j B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram 5
D-Regulator Restriction 4-Other (Explain)
IEEE Standard 803A-1983 i
E-Operator Training & License Examination F-Administrative i
G-Operational Error (Explain)
H-Other (Explain) j I
-