6 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of
)
)
Philadelphia Electric Company
)
Docket Nos. 50-352
)
50-353 (Limerick Generating Station,
)
Units 1 and 2)
)
APPLICANT'S RESPONSE TO THE BOARD'S REQUEST FOR INFORMATION CONCERNING POINT PLEASANT CONSTRUCTION on October 19, 1982 the Board requested that Applicant provide the following information regarding construction at Point Pleasant (Tr. 2496-98) :
1.
Set up work:
a.
Trailers for office and tools.
b.
Construction bulldozers and trucks.
c.
Barge sections for water work which would be assembled in larger
- sections, or at another location available by water to intake area.
d.
Removal of building near intake gate well.
2.
Non-contention. work:
a.
Site clearing and grading.
b '.
Road to gate well.
c.
Gate well construction.
d.
Canal crossing for construction access and canal dewatering.
I 8211230492 821119 PDR ADOCK 05000352 l
0 PDR e.
River access and piping for canal pumping.
f.
Intake line from gate well; under canal and to pumphouse, g.
Excavation for pumphouse, h.
Stockpile excavated material.
i.
Pumphouse structure.
j.
Transmission main from pumphouse to Bradshaw Reservoir.
k.
Bradshaw Reservoir and facilities including transmission mains.
Respectfully submitted, CONNER & WETTERHAHN, P.C.
/s/ Troy B. Conner, Jr.
Troy B. Conner, Jr.
Counsel for Applicant October 20, 1982 O
.