Motion to Direct NRC to Commence Special Insp Immediately of Dekalb Area Alliance for Responsible Energy/Sinnissippi Alliance for Environ Allegations of Unsafe Qa/Qc Practices at Plant
ML20069M219
Person / Time
Site: Byron  Constellation icon.png
Issue date: 11/18/1982
From: Cassel D
BUSINESS & PROFESSIONAL PEOPLE FOR THE PUBLIC INTERES, DEKALB AREA ALLIANCE FOR RESPONSIBLE ENERGY, SAFE ENERGY FOR NEW HAVEN
To:
Atomic Safety and Licensing Board Panel
Shared Package
ML20069M223 List:
References
NUDOCS 8211230486
Download: ML20069M219 (2)


Text

11/18/82

  • If; UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION 00LKETED BEFORE T!!E ATOMIC SAFETY AND LICENSING BOARD USNFC In the Matter of

)

82 NOV 22 #0:51

)

COMMONWEALTil EDISON COMPANY

)

Docket Nos. 50-454 ;pgggggAg,

)

50e455 h; 2. SERVic'E (Bryon Station, Units 1 and 2)

)

ii?ANCH MOTION TO DIRECT NRC STAFF TO COMMENCE SPECIAL INSPECTION DAARE/ SAFE, by its undersigned coun.sel, moves the Board to direct the NRC staff to commence its special inspection of DAARE/

1 SAFE's allegations of unsafe QA/QC practices at Byron.

In support of this motion, DAARE/ SAFE states as follows :

1.

On September 23, 1982, DAARE/FAFE moved the Board to reconsider its summary disposition of DAARE/ SAFE's contention number one relating to QA/QC at Byron.

DAARE/ SAFE's motion was based in part on affidavits of three former employees of contractors at Bryon, including a QA/QC Inspector and a QA auditor.

2.

On October 12, 1982, in its response to DAARE/ SAFE's motion, the NRC staff represented that it would commence "immediately" a special inspection of the allegations of DAARE/ SAFE's affiants, which it expected to complete "by December 1, 1982."

(Response at 7.)

3.

As detailed in the attached letter of this date from the a f fi ants ' counsel to the NRC staff, the special inspection has yet to commence in carnest.

8211230486 821118

%gQb

{DRADOCK 05000454 PDR

  • m,. A.

4.

The s taf f's foot-dragging on this special inspection prejudices DAARE/ SAFE's ability to prepare its case, especially since the Board has yet to rule on DAARE/ SAFE's pending, fully briefed September 23, 1982 motion to reconsider.

UllEREFORE, DAARE/ SAFE moves the Board to direct the NRC staff immediately to commence the special inspection and to complete it at the earliest reasonable date.

Novembe r 18 1982 Respectfully submitted, Douglass W. Cassel, Jr.

Jane !!. Whicher Attorneys for DAARE/ SAFE with respect to issues concerning quality assurance / quality control by:

d h-DouglasE W. Cassel, Jr.

I For Service:

Douglass W. Cassel, Jr.

Jane M. Whicher l

109 North Dearborn Suite 1300 Chicago, IL 60604 (312) 641-5570 i

-