Text
_ _.
t W ENTERGY f"'*"" [*;'"*"** '"*-
R. F. Durski W3F1-94-0081 A4.05 PR June 15, 1994 U.S. Nuclear Regulatory Commission ATTN:
Document Control Desk Washington, D.C. 20555
Subject:
Waterford 3 SES Docket No. 50-382 License No. NPF-38 Monthly Operating Report Gentlemen:
Attached is the subject monthly report which covers the operating statistics for the month of May,1994.
This report is submitted per Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38.
Very truly yours, 2
/.
(i b
pR{F.Julcsi
,/l
/
.j t., /
Direct'or Nuclear Safety RFB/ssf Attachment cc:
L.J. Callan, (NRC Region IV)
R.B. McGehee N.S. Reynolds F. Yost (Utility Data Institute, Inc.)
J.T. Wheelock (INPO Records Center)
/p NRC Resident Inspectors Office (WADM526) g 9406170378 940531
.n,,,L.L PDR ADOCK 050003B2 R
NRC MONTHLY OPERATING REPORT
SUMMARY
OF OPERATIONS WATERFORD 3 MAY 1994 The unit operated at an average reactor power of 99.7% and experienced no shutdowns or significant power reductions during the period.
j j
l PRESSURIZER SAFETY VALVE FAILURES AND CHALLENGES WATERFORD 3 During the month of May 1994, there were no pressurizer safety valve failures or challenges.
4 OPEF ATING DATA REPORT DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 DATE OF REPORT: JUNE,1994 COMPLETED BY:
T.S. BECKER TELEPHONE: 504-739-6683 OPERATING STATUS 1.
Reporting Period: May,1994 Gross Hours in Reporting Period: 744 2.
Currently Authorized Power Level (MWt): 3390 Maximum Dependable Capacity (Net MWe): 1075 Design Electrical Rating (Net MWe): 1104 3.
Power Level to which Restricted (if any) (Net MWe): N/A 4.
Reasons for Restriction (if any): N/A THIS MONTH YR TO DATE CUMULATIVE 5.
Number of Hours Reactor was Critical 744.0 2,485.8 63,585.8 6.
Reactor Reserve Shutdown Hours 7.
Hours Generator was On-line 744.0 2,430.3 62,718.5 8.
Unit Reserve Shutdown Hours 0- 9.
Gross Thermal Energy Generated (MWH) 2,515,334 8,057,936 207,086,413
- 10. Gross Electrical Energy Generated (MWH) 833,310 2,640,350 69,061,130
- 11. Net Electrical Energy Generated (MWH) 799,050 2,508,592 65,819,037
- 12. Reactor Service Factor 100.0 68.6 83.5
- 13. Reactor Availability Factor 100.0 68.6 83.5
- 14. Unit Service Factor 100.0 67.1 82.4
- 15. Unit Availability Factor 100.0 67.1 82.4
- 16. Unit Capacity Factor (using MDC) 99.9 64.4 80.4
- 17. Unit Capacity Factor (Using DER) 97.3 62.7 78.3
- 18. Unit Forced Outa0e Rate 0.0 0.8 3.4
OPERATING DATA REPORT DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 DATE OF REPORT: JUNE,1994 COMPLETED BY:
T.S. BECKER TELEPHONE: 504-739-6683 OPERATING DATA REPORT (Con't) 19.
Shutdowns Scheduled over next 6 Months (type, date and duration of each):
N/A 20.
If Shutdown at end of report period, estimated date of startup:
21.
Unit in Commercial Operation THIS MONTH YR TO DATE CUMULATIVE
- 22. Hours in Reporting Period 744.0 3623.0 76,128.0
- 23. Unit Forced Outage Hours 0.0 20.3 2,199.0 24.
Nameplate Rating (Gross MWe): 1200 25.
If Changes Occur in Capacity Ratings (Items Number 2 and 24) Since Last Report, Give Reasons: N/A
AVERAGE DAILY UNIT POWER LEVEL DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 DATE OF REPORT: JUNE,1994 COMPLETED BY:
T.S. BECKER TELEPHONE: 504 739 6683 MONTH MAY.1994 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-NET)
(MWo-NET) 1 1077 17 1065 2
1077 18 1076 3
1073 19 1079 4
1074 20 1078 5
1077 21 1078 6
1077 22 1079 7
1081 23 1079 8
1080 24 1077 9
1080 25 1077 10 1080 26 1078 11 1079 27 990 l
12 1080 28 1074 13 1081 29 1075 14 1080 30 1061 15 1077 31 1075 16 1078 lNSTRUCTIONS On this format, list the average daily unit power level in MWo-Net for each day in the reporting month.
Compute to the nearest whole megawatt.
4-UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 DATE OF REPORT: JUNE,1994 COMPLETED BY:
T.S. BECKER TELEPHONE: 504-739 4683 REPORT FOR MAY.1994 Type Method of Shutting F = Forced Duration Down the Reactor or Cause, Comments and Number Date S = Scheduled (Hours)
Reason (1)
Reducino Power (2)
Corrective Actions NONE i
(t) REASON (2) METHOD A=
Equipment Failure (explain) 1=
Manual B=
Maintenance or Test 2=
Manual Scram C=
Refueling 3=
Regulatory Restriction 4.=
Continuation frorn Previous Period E=
Operator Training and 5=
Power Reduction License Examination 6=
Other (explain)
F=
Administrative G=
Operational Error (explain)
H=
Other (explain)
,