Rept on Completion of Const.Plant Will Be Ready to Load Fuel During First Quarter 1982.Const & Preoperational Test Schedules Show 820223 as Most Likely Completion Date. Certificate of Svc Encl
ML20069L021
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 11/11/1982
From: Reveley W
HUNTON & WILLIAMS, LONG ISLAND LIGHTING CO.
To:
Shared Package
ML20069L019 List:
References
ISSUANCES-OL, NUDOCS 8211160348
Download: ML20069L021 (3)


Text

. LILCO, Novembar 11, 1982 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of )

)

LONG ISLAND LIGHTING COMPANY ) Docket No. 50-322 (OL)

)

(Shoreham Nuclear Power Station, )

Unit 1) ) -

COMPLETION OF CONSTRUCTION It continues to be LILCO's view that Shoreham will be physically ready to load fuel at some point during the first quarter of 1983. The Company's construction and pre-operational test schedules now show February 23rd as the most likely completion date.

Respectfully submitted, LONG ISLAND LIGHTING COMPANY l

W. T6ylor eveley, III Hunton & Williums Post Office Box 1535 l Richmond, Virginia 23212 DATED: November 11, 1982 8211160348 821111 l PDR ADOCK 05000322 G PDR

s' LILCO, November 11, 1982 CERTIFICATE OF SERVICE In the Matter of LONG ISLAND LIGHTING COMPANY (Shoreham Nuclear Power Station, Unit 1)

Docket No. 50-322 (OL)

I hereby certify that copies of (1) LILCO's Memorandum on the Use of Depositions to Increase Hearing Efficiency and (2) Completion of Construction were served today upon the following by first-class mail, postage prepaid, by Federal Express (as indicated by an asterisk), or by hand (as indicated by two asterisks): -

Lawrence Brenner, Esq.** Secretary of the Commission Administrative Judge U.S. Nuclear Regulatory Atomic Safety and Licensing Commission Board Panel Washington, D.C. 20555 i

U.S. Nuclear Regulatory Commission Atomic Safety and Licensing Washington, D.C. 20555 Appeal Board Panel U.S. Nuclear Regulatory

Dr. Peter A. Morris ** Commission

, Administrative Judge Washington, D.C. 20555

! Atomic Safety and Licensing Board Panel Atomic Safety and Licensing U.S. Nuclear Regulatory Board Panel Commission U.S. Nuclear Regulatory Washington, D.C. 20555 Commission Washington, D.C. 20555 Dr. James H. Carpenter **

Administrative Judge Daniel F. Brown, Esq.**

Atomic Safety and Licensing Attorney l

Board Panel Atomic Safety and Licensing l U.S. Nuclear Regulatory Board Panel l Commission U.S. Nuclear Regulatory 7

Washington, D.C. 20555 Commission Washington, D.C. 20555 t

i i

Bernard M. Bordenick, Esq.** David J. Gilmartin, Esq.

David A. Repka, Esq. Attn: Patricia A. Dempsey, Esq.

U.S. Nuclear Regulatory County Attorney Commission Suffolk County Department of Law Washington, D.C. 20555 Veterans Memorial Highway Hauppauge, New York 11787 Herbert H. Brown, Esq.** Stephen B. Latham, Esq.*

Lawrence Coe Lanpher, Esq. Twomey, Latham & Shea Karla J. Letsche, Esq. 33 West Second Street Kirkpatrick, Lockhart, Hill, P. O. Box 398 Christopher & Phillips Riverhead, New York 11901 8th Floor 1900 M Street, N.W. Ralph Shapiro, Esq.*

Washington, D.C. 20036 Cammer and Shapiro, P.C.

9 East 40th Street Mr. Mark W. Goldsmith New York, New York 10016 Energy Research Group 4001 Totten Pond Road Howard L. Blau, Esq.

Waltham, Massachusetts 02154 217 Newbridge Road Hicksville, New York 11801 MHB Technical Associates 1723 Hamilton Avenue Matthew J. Kelly, Esq.

Suite K State of New York San Jose, California 95125 Department of Public Service Three Empire State Plaza Mr. Jay Dunkleberger Albany, New York 12223 New York State Energy Office Agency Building 2 Empire State Plaza Albany, New York 12223

)

W. Tay r "R ley, III I

Hunton & Williams 707 East Main Street P.O. Box 1535 Richmond, Virginia 23212 DATED: November 11, 1982 l