Consumers Power sp - 32 9 Company Midland Project:
P.O. Box 1963, Midland, Michigen 48640. Aree Code 517 631-0951 January 12, 1983 f-IINC IPAL STAFF
- E 4 Y DJ l
l 4%
Mr. W. D. Shafer, Chief L ".PP l_ pe o
~
Midland Project Section 2MMf fiC0 "~
U.S. Nuclear Regulatory Commission
- MTP,
~l '-l('
Region III
'jl i
799 Roosevelt Road OL MILE
/g<
Glen Ellyn, IL 60137 MIDLAND PROJECT GWO 7020 REMEDIAL SOILS WORK AUIHORIZATION Pile: 0485.15 UFI: 12*32, 42*05*22*04 Serial: CSC-6495 The NRC and CPCo Work Authorization Procedure, Section 1.0 requires us to send to the NRC, at the beginning of each month, a list of items we plan on working on for the next 60-day period.
Due to recent NRC concerns regarding the information we have been sending to Dr. La:.dsman to facilitate his reviews of planned activities, we are hereby suspending subnittal of monthly activities lists until such time as we feel we are able to satisfactorily resume the process.
'Ihe suspension of submittal of the monthly activities list was discussed with you by our Mr. Wheeler on January 12, 1983, and you concurred with our proposed action.
D. B. Miller Site Manager DBM/GRJ/RMW/k1b l
Response Required: No
\\
g3280232830112 JAN 19 8 4
ADOCK 05000329 PDR fhi