Text

O 0;

m AlabamaPower March 7, 1983 the southem electre system M

n ro Director NRR V)

~

Nuclear Reactor Regulations USNRC Phillips Building 7920 Norfolk Avenue Bethesda, MD 20014

Dear Sir:

In accordance with Alabama Power Company Administrative Procedure FNP-0-AP-4, Control of Plant Documents and Records, attached is a memo and Procedure Request Form voiding FNP-0-EIP-20, Recovery - EOF.

Please remove and destroy all copies of this procedure from your files.

Pi3ase sign and return the Document Transmittal Forms as soon as possible to the following address:

Alabama Power Company Farley Nuclear Plant Box 470 Ashford, AL 36312 ATTN: Document Control Supervisor If you should have any questions, please call me at (205) 899-5156 Ext. 422.

Sincerely, Al

--- -- W, -,

r Qoe' B. (Iudspeth

[

FNP Document Control Supervisor a

JBH:hre cc: Larry W. Enfinger File fDOI 8303240112 830321 PDR ADOCK 05000349 F

PDR

e

'. i

- Document Transmittal Form Farley Nuclear Plant Production Department - Document Control Alabama Power L Te Date Liueb

\\;RR 4cW Ah %3wd53aw 3w Remarks:

\\ loin pcoewLwuD TRANSMITTED RETURN REQ'STED REMARKS NO.

REV.

Copy NO.

R EV.

Copy TITLE ANO/OR NUMBER CPS.

NO.

NO.

CPS.

NO.

NO.

FN P a p -ao 10 I

om%ru c 47 hA-I 8

e a

INSTRUCTIONS TO ADORESSEE

.enfy the documnets received agree witn the above description.

2. InCorDorste the transmitted documents into your files.
3. Documents or portions inereof presentiv in your possessionwhich are sucerseded by the documents hersby transmitted must be c:early m'arked "volo" or destroyed. If return of superseced documents is requested in the above " Return Recuested" column. attach the suoerseded documents to this form prior to
  • turning it.

Jgn in the space below indicating tnat you have completed these instructions and retum the routing copy of this form to the below address,

~w '~

Alabama Power Company j

WHITE - ROUTING COPY P. O. Drawer 470

's" Ashford. At 36312 s.gnature of Accressee YELLOW - SUSPENSE CCPY Attention: Occument Control Supervisor Form S 648

  • 7'"~ '

INTER DEPARTMENT. MEMORANDUM 6//8 d[$d @

~

To Town

/

~

~

.AT DATF 7/dlAbu2 FNP-dI-EXP-Bd cu.ar 0

m 7

"Y Y

Y Nm

/

CND

/) es n 1 on N

L f / i'l - V'C L /'- M ( )

p

\\

~

~

g

(

/,

i /-

,s

-x T

~l

/h 1/f J // JP/ J

)

~\\

a q

7 y

vi-1

/

~

n A

w 2

A A

A

$]

/IM2f7Dh W W Y W

/

s.

//

/

dheat#./nvrv.

//

~ //

//

d /n

.i

,,,,,,buaE kNd $

O/

7 l

l l

a

.k S

PROCIDURE'REQUIS's 20sM FNP-0-A?-1 1.

Procedure Number FNP-0-EIP-20 Revision Number Procedure Title Recoverv-EOF

\\

EC Safety Related C

Non-Safety Related C-

'New Procedure Requesa C

Procedure Revision, New Revision Number Change of Intenn Temporary Procedure Change, Effective until nexn permanent change, TCN C

Tesporary Procedure Change, Reg'd. by Plant Conditions, TCN C

Temporary Procedure Change, One Time Use XXX VOID THIS PROCEDURE IN ITS ENTIRETY 2.

Change Summary 2.1 Procedure Page Numbers Affected by Change N/s 2.2 Description of Changes N/A E

2.3 Reason for Change vuo_n_rTn_9n is no icneer needed since GO-ETP-Il5. Oe-esenintion of emp*eancy c1masification and Recnverr Tnitiation. kne been issued.

3.

Prepared By w) n B u a'

,c/uo reewnici,n g_22_g3 of Signature Title Date Revie>cd 37'[

I//m Sector Supervisor, 2-22-83

~

4 Signature /

Title

.Date 5.

Cross-Disciplinary /? ORC Review Groun Signature

-p Title Date Pott 11).s) '** " &

PrW 2-% u -f 3 l

6.

Temporary Change Approval (Signature /Date)

C Member Group Staff

/

C Shift Forecan

/

l C

Senior Reactor Coerator

/

O Plant Manager o

Final Approval (Signature /Date, required within 60 days of temporary approval)

SP' Group Supervisor 90/ 65 '[ '

/

Plant Superintendent c-

c. Mu A n

/1.M Fs O

MSAER l

C Vice President -

Nuclear Generation

/

O

/

C Plant. Manager

/

Eigure 1 Rev. '. 3 L.

J. ~ ' -

^

~~

FNP-0-AP-1 FARLEY NUCLEAR PLANT NUCLEAR SAFETY EVALUATION CECK LIST-

_(1)

-UNIT m,..a (2)

CECK LIST APPLICABLE TO:

FNP-0-ETo,n Revision TCN (3)

SAFETY EVALUATION - PART A The procedure, procedure change or modifcation to which this evaluation is applicable represents:

(3.1)

Yes No x

A' change to the plant as described in the FSAR7 (3.2)

Yes No x

A change to procedures as described in the FSAR7 (3.3)

Yes No x

A test or experiment not described in the FSAR?

(3.4)_ Yes-No x

A change to the Technical Specifications?

If the answer to any of the above questions is "Yes," complete Item (4) and attach a 10CFR50.59 evaluation.

If the answer to all of the above is "No," omit Item (4) and Item (9).

4 (4)

SAFETY EVALUATION - PART 3 (4.1) Yes No Will the probability of an accident previously evaluated in the FSAR be increased?

(4.2)

Yes No Will the consequences of an accident previously evaluated in the FSAR be increased?

t (4.3)

Yes No May the possibility of an accident which is different than any already evaluated in_the FSAR be created?

(4.4)

Yes No Will the probability of a malfunction of equipment important to safety previously evaluated in the FSAR be increased?

(4.5)

Yes No Will the consequences of a malfunction of-equipment important to safety different than any already evaluated in the FSAR be increased?

(4.6)

Yes No May the possiblity of a malfunction of equipment important to safety different than any already evaluated in the FSAR be created?

(4.7)

Yes No Will the margin of safety as defined in the basis to any Technical Specification be reduced?

If the answer to any of the above questions is "Yes," an unreviewed safety question is involved.

Explain the basis for each answer provided in Section 4.

c (5)

REMARKS:

(Attach additional pages if necessary)

(6)

PREPARED BY: k%1 DATE 2-22-83 t

(7)

REVIEWED BY:///// Mh6 DATE r_ r. : - 7 7 (8)

PORC REVIEW:~'r).Eg'U 2/ C DATE.2-2#-n i

(9)

NORB REVIEW:

DATE Distribution Original:

Document Control File A21 6226 i

Figure 3 Rev. 7

.