t r VERNONT YANKEE NUCLEAR POWER CORPORATION

,[

4 Ferry Road, Brattleboro, VT 05301-7002 ENGINE IN OFFICE

%0 MAPJ St rEET

,j 80L TON. MA M 740

($0m 779 07;1 February 14,1994 BVY 94-20 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555

References:

(a)

License No. DPR-28 (Docket No. 50-271)

(b)

Letter, USNRC to VYNPC, inspection Report No. 50-271/93-31, dated 12/21/93

Subject:

60 Day Response to Surveillance inspection Report No. 50-271/93-31 in Surveillance inspection Report No. 50-271/93-31 [ Reference (b)), the NRC noted that the Vermont Yankee surveillance test program was implemented in accordance with apprcved plant procedures and technical specifications applicable to the inspection.

The report also noted that the recent program upgrades adequately addressed all of the OSTI's noted program weaknesses.

However, the report identified a weakness with the tracking of safety-related pumps i

that required an increased frequency surveillance test in accordance with the Vermont Yankee Inservice Testing Program.

Weakness:

" Plant personnel used an informal document to ensure the proper surveillance frequency was performed instead of an existing procedure change form to update the computer automatic tracking system."

Response

To further strengthen the Vermont Yankee Inservice Testing Program, procedure AP 0164, " Operations Department inservice Testing," will be revised to directly reference procedure AP 4000, " Surveillance Testing Control," and to require that form VYAPF 4000.01, " Surveillance Testing Program Change Form," be completed and forwarded to the Surveillance Test Coordinator to revise the surveillance frequency. The SurveillanceTest Coordinator will then update the iSd 13@

PDR ADDCK 0500o271

[l,0) 94o2240o62 94o214 D

PDR i

1 J

, U'.S. Nuclear Regulatory CommissionVERMONT YANKEE NUCLEAR POWER CORPORATION February 14,1994 Page 2 computer automatic tracking system as required. These procedure changes are expected to be complete by March 1994.

We trust the information provided is adequate, however, should you have any questions or require additional information, please do not hesitate to contact us.

Sincerely, Vermont Yankee Nuclear Power Corporation

/-

!;f Y

Donald A. Reid Vice President, Operations cc: