Forwards Tentative Prioritization Schedule for Revising EOPs & Aops,Per Insp Rept 50-285/90-20 & 901220 Meeting W/Region IV
ML20066K906
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 01/30/1991
From: Gates W
OMAHA PUBLIC POWER DISTRICT
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
LIC-91-039R, LIC-91-39R, NUDOCS 9102060166
Download: ML20066K906 (2)


Text

.. _

L,.

.........r =$r. :

..........E.

'.Wr

'"" ' ' ' ~ ' ' ~~ '

-^-~~~7~'

Omaha Public Power District 444 South 16th Street Mall Ornaha, Nebraska 68102-2247 402/636-2000 l

January 30, 1991 LIC 91 039R U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station PI-137 Washington, DC 20555

Reference:

1.

Docket No. 50 285 2.

Letter from NRC (S. J. Collins) to OPPD (W. G. Gates) dated October 31, 1990 (Inspection Report 50 285/90-20)

Gentlemen:

SUBJECT:

Emergency Operating Procedures (E0Ps) and Abnormal Operating Procedures (A0Ps) Revision Prioritization During a meeting with NRC Region IV staff on December 20, 1990, Omaha Public Power District (0 PPD) committed to identify our priorities for revising the E0Ps/A0Ps for Fort Calhoun Station Unit No. 1.

Please find attached a tentative prioritization schedule for revising the E0Ps and A0Ps.

The revisions to the E0Ps/A0Ps will be done after the human factors rewrite of the Writer's Guide is completed.

If you should have any questions, please contact me.

Sincerely, l# E W. G. Gates Division Manager Nuclear Operations WGG/sel Attachment c:

LeBoeuf, Lamb, Leiby & MacRae R. D. Martin, NRC Regional Administrator, Region IV W. C. Walker, NRC Project Manager R. P. Mullikin, NRC Senior Resident Inspector

,102060166 91oiso

""14 'r'# e"*

' 1 ADOCK 05o 5

i;DR

1 Attachment o

~

i Prioritized Schedule for Revisions of EOPs and AOPs LQP1 Standard Post Trip Actions E0P 00 Optimal Recovery Procedures E0P-01 thru E0P 07 functional Recovery Procedure E0P 20 bOE1 Loss of Shutdown Cooling A0P 19 RCS Leak Procedure AOP 22 SG lube Rupture A0P 24 Loss of Vital Auxiliary Components AC Buses A0P 32-Instrument Buses A0P 16 Instrument Air A0P 17 Component Cooling Water AOP-il Raw Water A0P-18 Romainder of AOPs in numerical order Please note that the schedule may require alteration as the process continues.