Discusses Preliminary Evaluation of Relief & Safety Valve Testing,Per TMI Action Item II.D.1.Final Rept Expected for Unit 1 by Mar 1983 & for Unit 2 by Nov 1983.Evaluation for Block Valves Scheduled for Jan 1983
ML20066G685
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 11/16/1982
From: Lundvall A
BALTIMORE GAS & ELECTRIC CO.
To: Clark R
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.D.1, TASK-TM NUDOCS 8211230005
Download: ML20066G685 (2)


Text

_

~

BALTIM ORE GAS AND ELECTRIC CHARLES CENTER P.O. BOX 1475 BALTIMORE, MARYLAND 21203 ARTHUR E. LUNDVALL, JR.

November 16,1982 Vicc Paasiocsef Supptv Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Attn:

Mr. Robert A. Clark, Chief Operating Reactors Branch #3 j

Division of Licensing

Subject:

Calvert Cliffs Nuclear Power Plant Units Nos.1 & 2; Dockets Nos. 50-317 and 50-318 TMI Action Plan Item II.D.1 Gentlemen:

Three Mile Island Action Plan (NUREG-0737) Item II.D.1 addresses performance testing of reactor relief and safety valves. Testing supported by the nuclear industry through the Electric Power Research Institute (EPRI) has been completed, and we have received a report on the results of that effort. We are conducting an evaluation of the test data to determine what actions, if any, are appropriate for implementation at Calvert Cliffs Units 1 and 2.

Based on a preliminary evaluation of the data, we are confident that the safety and relief valves will function as designed at Calvert Cliffs. Mo/

tions, if any are required, can best be implemented on a deliberate schedule.

We plan to submit our final, plant-specific report per Item II.D.I.2.b no later than March of 1983 for Unit I and no later than November of 1983 for Unit 2.

Modifications, if required, will be scheduled for the Fall,1983, outage of Unit I and for the Spring,1984, outage of Unit 2.

Only limited block valve testing has been performed and the final report on this effort has not yet been received. Based upon delivery of the report before the end of l

1982, we plan to addrese Action Plan Item II.D.I.3 by completing and submitting a plant-specific evaluation of our block valves, based upon the available data, by the end of January,1983.

Very truly yours, t

,, m H. H. Miller for A. E. Lundvall, Jr.

Vice President-Supply

'0211230005 821'116 flIOh

~

PDR ADOCK 05000 P

Mr. R. A. Clark November 16,1982 AEL/MDP/gvg cc: