Interim Deficiency Rept Re RT Indications in Safety Injection Tanks & Reactor Pump Supports.Initially Reported on 820820.Evaluation of safe-end Indications by Ebasco & C-E Incomplete.Results Expected by 830114
ML20066E214
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 10/26/1982
From: Leddick R
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Sternberg D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
10CFR-050.55E, 10CFR-50.55E, G3-82-10965E, GO3-82-10965E, NUDOCS 8211120473
Download: ML20066E214 (2)


Text

A..,

Docket No. 50-397

~

50.55(e) Report 8

S82 ggy,/ jf f Washington Public Power Supply System Box 1223 Elma, Washington 98541 (206)482-4428

/

lot; October 26, 1982 G03-82-1096 U. S. Nuclear Regulatory Commission, Region V Office of Inspection and Enforcement 1450 Maria Lane, Suite 260 p

Walnut Creek, California 94596-5368 Attention:

Mr. D. M.

Sternberg Chief, Reactor Projects Branch No. 1

Subject:

POTENTIAL 10CFR50.55(eJ DEFICIENCY RT INDICATIONS, SAFETY INJECTION TANKS AND REACTOR PUMP SUPPORTS (D/N #23)

Reference:

Letter, G03-82-831, dated August 20, 1982, Mr. R. S. Leddick to Mr. D. M. Sternberg, same subject.

Ebasco, in conjunction with Combustion Engineering (CE), was directed by the Supply System to assure an evaluation of the safe-end indica-tions (associated with the subject deficiency) was performed per 10CFR50.55(e).

The referenced letter reported that this evaluation was not complete; however, upon completion, the results would be forwarded to your office by October 22, 1982. To date, the evaluation has not been completed.

It is anticipated that the results will be provided to your office by January 14, 1983.

The status of repair actions taken is as follows:

o CE has submitted an ASME Section XI repair plan documenting the rework required per the disposition of the original NCR.

e The repair plan was approved by the Supply System and the work commenced on September 13, 1982.

e Grinding operations revealed additional indications that were not indicated on the RT film. CE elected to remove the indica-tions rather than evaluate the relevancy of the indications.

e Final PT of the excavation areas was accepted by CE QA Representa-tives and the Supply System on October 13, 1982.

8211120473 821026 PDR ADOCK 05000397 k

yl)

S PDR l

"J

A-Mr. D. M. Sternberg October 26, 1982 Page 2 G03-82-1096 e Excavated areas were fully mapped on the table attached to the repair plan to show the length, width and depth of the indications.

e Carbon steel base metal was encountered during the grinding operations.

Therefore, an additional CE welding procedure was required. The procedure was approved by the Supply System and added to the repair plan.

e The welding, required to build up the excavated areas, commenced on October 13, 1982.

It is expected that the weld repair and PT will be completed by the first week of November,1982.

e CE's initial evaluation has determined that the defects were not significant (i.e.,.not reportable per 10CFR50.55(e) ).

Should you have any questions or desire additional information, please contact me directly.

Sj7b O. -

R. S. Leddick (761)

Program Director, WNP-3 DRC:nj cc: Mr. J. Adams - NESCO Mr. D. Smithpeter - BPA Ebasco - New York WNP-3 Files - Richland l