Updates 790427 & 0803 Responses to IE Bulletin 79-08,Item 6, Daily Position Verification of ECCS Valves. Frequency of Position Verification of ECCS Valves Reduced from Once Per Day to Once Per Month
ML20066C237
Person / Time
Site: Dresden, Quad Cities, 05000000
Issue date: 08/31/1982
From: Swartz E
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20066C217 List:
References
REF-SSINS-6820 4925N, IEB-79-08, IEB-79-8, NUDOCS 8211090420
Download: ML20066C237 (2)


Text

  • '

Commonwrith Edison

[o!DN i Y. On3 First Nationti Plus. Chicags--Hhnois

~'

C I" Addrtss R: ply to: Post Offica Box 767

. Chic go, Illinois 60690 Augus t 31, 1982 Mr. James G. Keppler, Regional Administrator Directorate of Inspection and Enforcement - Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Subject:

Dresden Station Units 2 and 3 Quad Cities Station Units 1 and 2 IE Bulletin No. 79-08 Item No. 6 Daily Position Verification of ECCS Valves NRC Docket Nos. 50-237/249 and 50-254/265 Re ferences (a): Cordell Reed letter to J. G. Keppler dated April 27, 1979 (b): Cordell Reed letter to T. A. Ippolito dated Augus t 3, 1979 (c): J. G. Keppler letter to Byron Lee, Jr.

dated April 14, 1979 (d): T. A. Ippolito letter to D. L. Peoples dated March 10, 1980

Dear Mr. Keppler:

References (a) and (b) provided the Commonwealth Edison Company commitments concerning safety-related valve position verification in response to Reference (c) IE Bulletin No. 79-08 Item 6 for our Dresden and Quad Cities Stations. Subsequently, Reference (d) provided the results of the NRC Staff evaluation which concluded that our commitments satisfied the intent of IE Bulletin 79-08 for this Item 6.

~

In particular, we indicaEed that the positions of vital manual ECCS valves are controlled by the use and documentation of locks on the handwheels. Additionally, we committed to implement a procedure for daily verification that all accessible ECCS valves in the main flow paths are in their proper positions.

8211090420 821104 SEP 2 1832 PDR ADOCK 05000237 G PDR

l Since the implementation of this procedure in 1979 at both

~

Dresden and Quad Cities Stations, the daily valve position verification has never identified any locked manual ECCS valves as being out of proper position. For this reason, and the fact that thi position of these valves is controlled by chains and padlocks, we believe that daily surveillances are no longer warranted in order to address the original NRC Staff concerns regarding valve position verification.

In view of the above, we f eel that monthly verification is now a more appropriate response to IE Bulletin 79-08 Item 6 concerning manual ECCS valves. Therefore, we intend to reduce the frequency of position verification on locked, manual valves in the ECCS systems from once per day to once per month at our Dresden and Quad Cities Stations. Our current position verification practice on other valves in the ECCS systems will remain unchanged.

Please address any questions that you or your staff may have concerning this matter to this o f fice.

Very truly yours, E. ouglas Swart Nuclear Licensing Administrator cc: Region III Inspector - Dresden Region III Inspector - Quad Cities Darrell G. Eisenhut - D/DL 4925N 1