Order Extending Const Completion Dates for CPPR-130 from 820601 to 841001 & CPPR-131 from 831101 to 860401
ML20065U227
Person / Time
Site: Byron  Constellation icon.png
Issue date: 10/12/1982
From: Eisenhut D
Office of Nuclear Reactor Regulation
To:
COMMONWEALTH EDISON CO.
Shared Package
ML20065U229 List:
References
NUDOCS 8211040041
Download: ML20065U227 (4)


Text

__

7590-01 UNITED STATES NUCLEAR REGULATORY COMMISSION COMMONWEALTH EDISON COMPANY BYRON STATION, UNITS 1 AND 2 DOCKET NOS. 50-454 AND 50-455 ORDER EXTENDING CONSTRUCTION COMPLETION DATES Commonwealth Edison Company is the holder of Construction Pemit Nos.

CPPR-130 and CPPR-131 issued on Decenber 31, 1975 by the U. S. Nuclear Regulatory Commission for construction of the Byron Station, Units'1 and 2 to be located in Ogle County, Illinois, approximately 17 miles southwest of Rockford, Illinois.

By letter, dated April 19, 1982, Commonwealth Edison Company filed a request for extension of the latest construction completion dates for the Byron Station, Units 1 and 2 Construction Pemits.

It was requested that Construction Pemit

' No. CPPR-130 for Unit 1 be extended from June 1,1982 to October 1,1984 and Construction Pemit No. CPPR-131 for Unit 2 be extended.from November 1,1983 i

to April 1,1986. The reasons given for the requested extension in time were:

(1) extended construction period caused by the need to install larger quantities of eterial and equipment than originally contemplated as well as changes in NRC regulatory requirments some of which resulted from the Three Mile Island incident, (2) improvements in the manner of implementing NRC requirements including cvX$

increased amounts of design wort and installation labor required to complete i

-e n,

.O installation of various components, pipes, cables, and structural mecbers, l

E l

.O and (3) implementation of work requirements at a pace consistent with the need g:s:

l o8 to spread financial requirenents evenly throughout the construction period

.80 in order to maintain annual financial requirements within the capabilities 5

ga.<

of Commonwealth Edison Company.

omcs)

SURNAME) care >

OFFICIAL RECORD COPY usa m m i 3m.

j. nne ronu m pm sacu oua

. 7590-01 This action involves no significant hazards consideration, good cause has been shown for the delays, and the requested extension is for a reasonable period, the bases for which are set forth in the staff's safety evaluation for this extension.

The Comission has deter;nined that this action will not result in any significant environnental impact and, pursuant to 10 CFR 51.5(d)(4), an environmental impact statement, or negative rieclaration and environmental impact appraisal, need not be prepared in connection with this action.

The applicant's letter, dated April 19, 1982, and the NRC staff's safety evaluation supporting the Order are available for public inspection at the Comission's Public Document Room,1717 ti Street, H. W., Washington, D. C.

20555 and at the Rockford Public Library, 215 ti. Wyman Street, Rockford, Illinois 61103.

IT IS HEREBY ORDERED that the latest construction completion date for CPPR-130, Unit 1, be extended from June 1,1982 to October 1,1984 and for CPPR-131, Unit 2, be extended fron Novenber 1,1983 to April 1,1985.

FOR THE IluCLEAR REGULATORY CO}rlISSION

(

~

Darrell G. Eisenhut or Division of Licensing I

Date of Issuance: OCT 121982 l

l l

l l

l SEE PREVIOUS ORC FOR CONCURRENCES.

s n

.D.L... k........

.D..L..:.L..B..#.1 *.O..E.L..D..*..............

.D..L...:.L. B...#.1.*.........

O..

omer >

MRu rook /l 1SChesnut SGoldberg BJYoungblood T ak hut sunuurt

.........../. 8 2 10( Y~~ i'67.............../.s/sE".".."

T6/W/E2"..'...Td/ /82 10/../82 10/

oare >

......i.................

l Nac ronu sie 00-803 nacu o24o OFF1ClAL RECORD COPY usaposui-mE l

s m

e 7590-01 This action involves no significant hazards consideration. good cause has been shown for the delays. and the requested extension is for a reasonable

/

period. the bases for which are set forth in the staf f's safety evaluation for this extension.

The Commission has determined that this action will n t result in any significant environmental impact and. pursuant to 10 C 51.5(d)(4), an enviromental impact statement, or negative declarati n and environmental impact appraisal. need not be prepared in connection with his action.

The applicant's letter, dated April 19.19

, and the NRC staff's safety evaluation supporting the Order are availabl for public inspection at the Commission's Public Document Room.1717 H Street. H. W.. Washington. D. C.

20555 and at the Rockford Public Libra,y. 215. Wyman Street, Rockfords Illinois 61103.

IT IS HEREBY ORDERED that the ia, test construction completion date for

/.

CPPR-130, Unit 1, be extended from June 1,1982 to October 1,1984 and for CPPR-131, Unit 2, be extended from/

November 1,1983 to April 1,1986.

/

Darrell G. Eisenhut. Director Division of Licensing Date of Issuance:

/

t

/

/

/

j i

  • See previous yellow.

/

[/3 1

DL:LB#1*

DL:LB#1 OELDf DLE 6

DL:AD/L DL:DIR OFFICE )

........B..........

Ru) brook /y.t SChesnu.t....

SGo.ldb

...Bhaungbl.co<1 T!Govak

..DEisenhut...

sunume >

Z/.982,.....,,yggza2,,,,,,,

7/2 fza2,,,,, g/,paz,

,?z..za2 7z..za2,,,

om>

NRC FOR%4 318 (10-80) NRCM O24J OFFICIAL RECORD COPY uso m isei-m mo

' o.

. 7590-01 This action involves no significant hazards considoration, goodMause has been shown for the delays, and the requested extension is for a reasonable period, the bases for which are set forth in the staff's safe evaluation

\\

y

, y'*

for this extension, The preparation of an enviromental impact sta ent for this particular action is not warranted because there-wk 1 be no ignificant environmental impact attributable to the Order other th'an that wh has already been predicted and evaluated in the Commiss' ion's Final E vironmental Statement related to operation of the By,ron 5 ation, Units and 2 (HUREG-0848) which was issued in April 1982, The Commission has determi ed that this action will not result in any significant environmental im 'act and, pursuant to 10 CFR 51.5(d)(4), an envirorrsental impact sta

.ent, or negative declaration and enviromental impact appraisal, need not he epared in connection with this action.

The applicant's letter, dated April 19, 1982, and the NRC staff's safety evaluation suppo ing the Order are available for public inspection at the Commi ssion's P blic Document Roem,1717 H Street, H. W., Washington, D. C.

20555 and at the P ckford Public Library, 215 N. Wyman Street, Rockford, Illinois 61103.

t IT I llEREBY ORDERED that the latest construction ccapletion date for CPPR-13, Unit 1, be extended from June 1,1982 to October 1,1984 and for CPPR-31, Unit 2, be extended from Hovember 1,1983 to April 1,1986.

Darrell G. Eisenhut, Director

/

Division of Licensing Date of Issuance:

DL:LB#1 DL:LB#1 OELD DL:LB#1 DL:AD/L orrece)

.g

..g..

.g.

sunume >

..b W

one>....k..}.1.,..........k.. \\..f3h.

OFFICIAL RECORD COPY usom mi-mm nac ronu sia oo.aopecu o24o