AVERAGE DAILY UNIT POWER LEVEL 50-250 DOCKETNO.
T rkey Point 3 E'IT DATE 9-15-82 P. L. Pace COMPLETED BY
]
TELEP110NE (305) 552-3654 s
MONTH August, 1982 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL IMWe Net)
-(MWe-Net) g 0
675 g7 2
0 3
0 682 39 0
4 20
- ^ -
0 o/o 5
21 6
0 670 22 229 668 7
23 67 f,-
669 8
24 668 673 9
25 578 670 10 26
-11 8
670 27 668 672 12
.,8 672 669 13 29 14 671 671 30 666 675 15 33 16 670 INSTRUCTIONS On this forma.hsr the ascrage daily unit power lessiin MWe Nei for ca:h day in the reporting month. Compute to the nearest whole inegawait.
(9/77) 8211020221 820915 PDR ADOCK 05000250 R
OPERATING DATA REPORT DOCKETNO. 50-250 DATE 9-15-82 COllPLETED BY P. L. Face TELEPHONE (305) 552-3654 OPERATING STATUS
- 1. Unit Name:
Turkey Point 3 Notes Unit 3 returned to full
- 2. Reporting Period:
A ngne t 1982
- 3. Licensed Thermal Power (MWt):
2200 power after an outage for
- 4. Nameplate Rating (Gross MWe):
760 d a pm Mm
- 5. Design Electrical Rating (Net MWe):
693
- 6. Maximum Dependable Capacity (Gross MWe):
680
- 7. Maximum Dependable Capacity (Net MWe):
646
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
- 9. Power Level To Which Restricted.lf Any (Net MWe):
- 10. Reasons For Restrictions. If Any:
j This Month Yr.-to.Date Cumulatise I1. Hours In Reporting Period 744 5831 85,376.6
- 12. Number Of Hours Reactor Was Critical 607.3 Z994.9 Jo,'>>
- 13. Reactor Reserve Shutdown Hours U
I4. Hours Generator On-Line 562.2 2858.1 56,749.1
- 15. Unit Reserve Shutdown Ilours 0
0 121.8
- 16. Gross Thermal Energy Generated (MWH) 1.237,180 6,225,007
_ LD,4ZZ. 36Z
- 17. Gross Electrica! Energy Generated (MWH) 393,895 2,004,29)
Jo,ove,ytv
- 18. Net Electrical Energy Generated (MWil) 373,145 1,894,350 34,716,016
- 19. Unit Service Factor 75.6 49.u oo.a
- 20. Unit Asailability Factor 75.6 49.0 00.0
- 21. Unit Capacity Factor (Using MDC Net) 77.6 av.a 37
- 22. Unit Capacity Factor (Using DER Net) 72.4
%.9
- x. o
- 23. Unit Forced Outage Rate 21.9 16.2 5.7
- 24. Shutdowns Schednfed Oser Next 6 Munths IType. Date.and Duration of Eacht:
I
- -. ~ - -.
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26. Units In Test Status ll*rior to Connnercial Operation):
Foreca<t Achiesed INITIA L CRIIICA LITY INIfi \\L ElfCTRICITY
( OM\\1LRCIAL OPERATION (9/77 9
=
DOCKET NO. 50-250 UNITS!!UTDOWNS AND POWER REDUCTIONS UNITNAME Turkey Point 3 DATE 9-15-82 COMPLETED BY P. L. Pnco REPORT MONTH August. 1982 TELEPI(ONE (305) 55?-us4
=
',5 g 3
4.Y 5 Licensee
'j g 5 ",,
Cause & Corrective 4
.5 i s Event is b gy 53 Action to No.
D.ite c.
~=
S f:
s 3 5 =s
. Report :
to O 5V Prevent Recurrence G
6 e
12 820721 F
157.8 A
4 CB FDTOIOC Reactor tripped due to loss of reactor coolant pump which tripped due to instantaneous overcurrent. The re-actor coolant pump motor was replaced.
(Continued from previous month.)
13 820810 S
24.1 A
1 CH VALVEX:
Unit 3 was removed from service to re-pair feed pump drain valve and to re-pair / adjust the turbine control valve. Unit 3 was then returned to full power.
a I
2 3
4 F: Forced Reason:
Method:
Exhibit G. Instructions S: Scheduled A Equipment Failure (Explain) 1 Manual for Preparation of Data B Maintenance of Test 2 Manual Scram.
Entry Sheets for Licensee C Refueling 3-Automatie Scram.
Event Report (LER) File (NuREG.
D Regulatory Restriction
$0ther (Explain) 01611 E-Operator Training i Ueense Examination F-Admmistrative p
5 G. Operational Error (Explain) s A o a o r u n ve.,..c/
Exhibit ! Same Souree (9/77)
Il Other (Explain)
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.
50-250 UNIT Turkey Point 3 DATE 9-15-82 COMPLETED BY P. L. Pace TELEPHONE (305) 552-3654 REPORT MONTII August, 1982 Unit 3 returned to operation following repair of the 3A reactor coolant pump on August 7, 1982. There was a brief outage on August 10, 1982, to repair the 3A steam generator feed pump drain valve and to adjust the num-ber 3 turbine control valve.
Inspections and requirements of IE Bulletins and NUREG-0737 are continuing.
Florida Power;4 Light Company commitments for NUREG-0737 implementation are continuing. IRefer to correspondence between FPL and NRC for additional infonnation.
~
l
AVERAGE DAILY UNIT POWER LEVEL
~
DOCKET NO.
50-251 UNIT Turkey Point 4 9-15-82 DATE COMPLETED BY P. L. Pace (305) 552-3654' TELEPilONE s
MONTH August, 1982 DAY AVERAGE DAILY POWER LEVEL DAY AVER AGE DAILY POWER LEVEL IMWe Net)
-(MWe-Net) 1 660 669 y7 653 2
673 18 3
657 673'
~
,g 19 4
662 668 20 664 5
665 2j 6
676 659 22 674 7
656 23 4
8 670 659 24 669 9
661 25 669 10 660 26 670 658 27 450 12 660 28 665 13 660 39 14 667 660 30 660 15 658 33 664 16 INSTRUCTIONS On this forenar, tar the average daily unit power leselin MWe Net for <2:h day in the reporting wnth. Compute to the nearest whiile megawart.
89/77)
OPERATING DATA REPORT DOCKET NO. 50-251 DATE 9-15-82 COMPLETED BY P. L. Pace TELEPif0NE (305) 552-3654 OPERATING STATUS
- 1. Unit Name:
Turkov Point 4 Notes Unit 4 operated at
- 2. Reporting Period:
August, 1982 essentially full power except 2200 for a Mef outage on 8WM.
- 3. Licensed Thermal Power (MWt):
760
- 4. Nameplate Rating (Gross MWe):
- 5. Design Electrical Rating (Net MWe):
693
- 6. Maximum Dependable Capacity (Gross MWe):
680 646
- 7. Maximum Dependable Capacity (Net MWe):
- 8. If Changes Occurin Capacity Ratings (Items Number 3 Through 7) Since Utst Report.Give Reasons:
- 9. Power Level To which Restricted,if Any (Net MWe):
- 10. Reasons For Restrictions,If Any:
This Month Yr.-to-Date Cumulative II. Ilours In Reporting Period 744 5831 79,104
- 12. Number Of flours Reactor Was Critical 741.0 49/4./
Jo, m.o
- 13. Reactor Reserve Shutdown flours 0
0 166.6
- 14. Ilours Generator On-Line 738.2 491/.3 a7,uut.7
- 15. Unit Reserve Shutdown !!ours 0
v M.2
- 16. Gross Thermal Energy Generated (MWil) 1:626.902 10,770,977 119,987,.600
- 17. Gross Electrical Energy Generated (MWH) 513,880 3,445,925 35,10/,994
- 18. Net Electrical Energy Generated (MWil) 488,854 3,272,03z Jo,tou,otu
- 19. Unit Service Factor 99.2 84.3 72.1
- 20. Unit Availability Factor 99.2 84.3
/z.I
- 21. Unit Capacity Factor (Using MDC Net) 101.7 56.9 go
- 22. Unit Capacity Factor (Using DER Net) 94.8 c1.u uu.v
- 23. Unit Forced Outage Rate
- D
- 24. Shutdowns Scheduled Over Next 6 Months IType.Date.und Duration of Each t:
Steam Generator Repair Project, mid-October,1982, 9 months.
l
- 25. If Shnt Down At I:nd Of Report Period. Estimated Date of Startup:
- 26. Unin In Test Status IPrior to Connnercial Operation):
Forecast Achieved INi fl A L CRil'ICA Li'l Y INI F1 \\ L El.FCIRICITY
( OM\\lLRCI A L OPER ATION 08/776 e.
.--g
, ~ -
f-g
DOCKETNO. 50-251 UNITSIIUTDOWNS AND POWER REDUCTIONS UNITNAME Turkev Point 4 DATE
"-D-"
COMPLETED BY P. L. Pace REPORTMONTH August, 19_82 TELEPHONE (305) 552-3654 e.
,5 ?
S
$ $ 5' Licensee 3 r,,
$*u Cause & Cotteetive Nii.
DJie i
~g 4
.5 s E Event 4' b 11 E.7 Action to F-yE 5 ;5 =s
. Report :
mV EO Prevent Recurrence a
u O
14 820812 F
5.8 G
3 CH VALVEX Reactor tripped on high steam generator level due to damage to a feedwater regulator valve. control cable. The cable was repaired dnd the unit was returned to service.
1 3
I 2
3 4
F: Forced Reason:
Method:
Exhibit G Instructions S: Scheiruled A. Equipment Failure (Explain)
- 1. Manual for Preparation of Data B Maintenance of Test 2 Manual Scram.
Entry Sheets for Licensee C Refueling 3.Automatie Scram.
Event Report (LER) File (NUREG.
D. Regulatory Restriction 9-Other (Explain) 0161)
E-Operatiyr Training & License Examination F Admmistrative p
5 G Operational Error (Explain) s
/.o ao a.4cv<.n.cl Exhibit ! Same Source (9/77)
Il Other(Explain) -
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.
50-251 UNIT Turkey Point 4 DATE 9-15-82 COMPLETED BY P. L. Pace TELEPHONE (305) 552-3654 REPORT MONTH August, 1982
^
Unit 4 operated at essentially full power for the entire monch except for a brief outage on August 12, 1982, due to construction damage to a feedwater regulating valve control cable.
Inspections and requirements of IE Bulletins and NUREG-0737 are continuing.
Florida Power & Light Company commitments for NUREG-0737 implementation are continuing. Rgfer to correspondence between FPL nad NRC for additional info rmation..;;;*
I
AVERAGE DAILY UNIT POWER LEVEL 50-335 DOCKET NO.
St. Lucie 1 UNIT 9-15-82 DATE COMPLETED BY P. L. Pace (305) :552-3654 TELEPilONE s
MONTH August, 1982 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL IMWe-Net)
~
.(MWe Ner) 838 1
826*
17 801 829*
2 38 830 63za 3
.t 19 4
833 834*
20 832 835 5
y, 6
837 834 22 7
837 835 3
3
...03 834 8
9 834 838 25 10 834 841 36 833 840
'II 27 12 833 838 28 831 836 13 39 834 835 14 30 15 833 833 31 482 16
- Indicates some steam used for St. Lucie Unit 2 testing.
I INSTRUCTIONS On this formai.hst the aser.sge daily unit power leselin MWe.Sei for ca:h day in the reporting anonth. Compute to the nearest whole enepwart.
19/771 O
OPERATING DATA REPORT
'50-335 DOCKET NO.
DATE 5'-13-6Z COMPLETED BY P. L-Pace TELEPilONE (305) 552-3654 OPERATING STATUS
- 1. Unit Name:
St. Lucie 1 Notes Unit 1 operated at es-
- 2. Reporting Period:
August, 1982 sentially full power except 2700 for a M ef outage on 8 M 82.
- 3. Licensed Thermal Power (MWt):
- 4. Nameplate Rating (Gross MWe):
890 See Unit Shutdowns and Power
- 5. Design Electrical Rating (Net MWe):
830 Reductions" Report for 862 details.
- 6. Maximum Dependable Capacity (Gross MWe):
- 7. Ma,imum Dependable Capacity (Net MWe):
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
- 9. Power Lesel To Which Restricted. If Any (Net MWe):
- 10. Reasons For Restrictions,if Any:
This Month Yr to.Date Cumulative
- 11. Ilours In Reporting Period 744 5831 49,919
- 12. Number Of Hours Reactor Was Critical
/ 6.9 M.;-
w, m.<_
- 13. Reactor Reserve Shutdown Hours n
0 205.3
- 14. Ilours Generator On-Line 737.8 5354.8 39,367.7
- 15. Unit Resene Shutdown flours 0
0 39.3
- 16. Gross Thermal Energy Generated (MWil) 1,965,785*
14,267,450 97,591,369
- 17. Gross Electrical Energy Generated (MWil) 644,230 4,683,540 31,/41,633
- 18. Net Electrical Energy Generated (MW11) 611,329 4,441,04Z 29,W U,3cv
- 19. Unit Service Factor 99.2 91.c e o. 's
- 20. Unit Availability Factor 99,2 91.5 78.3
- 21. Unit Capacity FactoriUsing MDC Net) 100.6 95.0
/6.9
- 22. Unit Capacity Factor IUsing DER Net) 99.0 92.9
/4
- 23. Unit forced Outage Rate
- 24. Shutdowns Scheduled Oser Ne.st 6 Months 11ype. Date.and Duratio i of Each t:
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26. Units In Test Status IPrior to Commercial Operationi:
Forecast Achiesed INillA L CRITICA LITY INI flT L ELEC TRICITY CO\\l\\lLRCI A L OPER ATION
- 368 Mull (thermal) used for St. Lucie Unit 2 testing.
(9/74 g
9 DOCKETNO. 50-3.15 UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME St. Lucie 1 DATE 9-15-82 REPORT MONTH August, 1982 COMPLETED 11Y P. L. Pace TELEPHONE (305) 552-3654 w.
.5 ?
3
..y i Licensee 3 r,,
Sg Cause & Corrective L.
D.it e i
.5 i 5 Event 43 b g?
53 Action to S
$~
ji gg g
. Report :
mO EO Prevent Recurrence e
O O
03 820816 F
6.2 H
2 335-82-37 EB RELAYX Unit was manually tripped following loss of power to 4.16 kV Bus. A load shedding relay in the vital /non-vital tie breaker had been jarred. The bus was re-energized and the unit returned to power.
in I
2 3
4 F: Forced Reaso1:
Method:
Exhibit G Instructions S: Sched'uted A.Eqdpment Failure (Explain) 1 Manual for Preparation of Data B.Malatenance of Test 2 Manual Scram.
Entry Sheets for Licensee C Refueling 3 Automatie Scram.
Event Report (LER) File (NUREG.
D. Regulatory Restriction
$0ther (Explain) 0161)
E Operatiir Training & License Examination F Adam,strative p
i 5
G.Op< rational Error (Explain) c Ao ao a.4uue.,..cl E.shibit ! Same Source (9/77}
Il 01her(Explain)
r.
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.
50-335 UNIT St. Lucie Unit No..I DATE 9-15-82 COMPLETED BY P. L. Pace TELEPHONE (305) 552-3654 REPORT MONTII August, 1982 Unit 1 operated at essentially full power for the entire month except for a brief outage on August 16, 1982. See the " Unit Shutdowns and Power Reductions" report for details.
Major Safety-related maintenance activities performed during the month included:
Component; cooling water system maintenance.
1 Testing of the 4.16 kV load shedding relay on the vital /non-vital bus tie breaker which caused a unit trip.
Maintenance of the "A" inverter.
Inspections and requirements of the IE Bulletins and NUREG 0727 in progress.
Florida Power & Light Company commitments for NUREG-0737 implementation are continuing. Refer to correspondence between FPL and NRC for ad-ditional information.
1 L..
.-