ML20065S843

From kanterella
Jump to navigation Jump to search

Forwards Addl Info Re Evaluation of Loss of Offsite Power, Per 901113 Response to Station Blackout Safety Evaluation. Rev to SE to Reflect Info & Reestablish Coping Duration as 4 H Requested
ML20065S843
Person / Time
Site: Calvert Cliffs  
Issue date: 12/13/1990
From: Creel G
BALTIMORE GAS & ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
TAC-68525, TAC-68526, NUDOCS 9012260106
Download: ML20065S843 (4)


Text

_

l G ALTIMORE OAS AND ELECTRIC CHARLES CENTER e P.O. BOX 1475

  • BALTIMORE. MARYLAND 21203 1475 GE040E C CREEL V<c t Pas siot wr NCtf AM rht*0v i 3 f> 0 F 6 D 4 4 S ti December 13,1990 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:

Document Control Desk

SUBJECT:

Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nos. 50 317 & 50-318 Supplement to the Station Blackout Safety Evaluation Response (TAC Nos. M525 and M52M

REFERENCES:

(a)

Letter from Mt. G. C. Creel (BG&E) to NRC Document Control Desk, dated November 13,1990, Response to Station Blackout Safety Evaluation Gentlemen:

This letter provides the additionalinformation concerning our evaluation of the loss of offsite power described in Reference (a). The primary issue raised in the NRC Safety Evaluation for station blackout concerned the reliability of our offsite power sources. Specifically, a transistor failure caused the loss of an offsite line following a ground fault.

During a meeting with the NRC Staff on November 1,1990, the loss of offsite power event was discussed. Several issues remained unclear at the conclusion of that meeting. The main concern was the ability of the relay panel components to withstand the effects of the surge current following a ground fault. The attachment provides more detail concerning the response of the relay panel to the ground fault experienced on July 23,1987. This information supports the determination that the equipment failure was random and not symptomatic of inadequate surge protection or other design flaw. Based on this information, we request that the NRC revise the Station Blackout Safety Evaluation for Calvert Cliffs to reflect this information and reestablish our coping duration as four hours.

k Q\\

l()y(}#

W2ggg gggg;,

e

l Document Control Desk December 13,1990 Page 2 should you have any further questions regarding this matter, we will be pleased to discuss them with you.

Very truly yours,

)

l

'O

/

~

, (,

GCC/ PSF / psf /dirn

Attachment:

As Stated cc:

D. A. Brune, Esquire J. E. Silberg, Esquire R. A. Capra, NRC-D. G. Mcdonald, Jr., NRC T. T. Martin, NRC L E. Nicholson, NRC R. I. Mc1.can, DNR ir-i-

A'ITACilMENT EVAL,UATION OF TRANSISTOR FAILUltE FOLLOWING A GROUNI) FAUllr This attachment is prepared in a question and answer format with the questions derived from NRC concerns stated during a meeting held with the NRC Staff on November 1,1990.

,Questfort When was the static relay panel last tested before the 1987 loss of offsite power event?

Itesponse The relay panel was tested on March 16,1987, and the transistor was operational at i

that time.

Question Will the same tyi'c of relay panel be used for the future 500 kv transmission line between Calvert Cliffs and PEPCO's Chalk Point generating station?

Rnvonse g

The equipment used on the existing 500 kv line at Calvert Cliffs is no longer manufactured by General Electric. We have not yet purchased relay panels for the proposed 500 kv tic line to Chalk Peint, and when purchased, they will be different from the existing equipment.

Question Ilow many faults have occurred on the 500 kv and 230 kv system where these static panels are used? Did this particular transistor fait during these faults?

Huponse System records are not readily available for the period prior to 1979. Ilowever, a review of the system operator logs from 1979 through the present for breaker operations on these lines was performed. This review showed that this transistor has never failed as a result of being subjected to fault currents, t

1

A'ITACIIMENT EVALUATION OF TilANSISTOR FAILURE FOLLOWING A GROUND FAULT The data shows there were et least 36 events where these lines experienced a fault cuirent.

One of these was the Calve Cliffs loss of offsite power event. In many cases, the faults were momentary and the breaker.,-chsed immediately. Not all of the faults, or suspected faults, resulted in loss of service bcue parallel lines remained in senice. In a few cases, such as the evero a' Calvert Cliffs, generation was lost. In the seven events other than the Calvert Cliffs, vent wNe breakers operated on parallellines, this transistor did not malfunction. It should '.>c not. ' hat these relays also sense fault currents due to short circuits elsewhere in the system v,. u.ast operate properly to prevent trips in these cases. Therefore, the relays have bec'. halic,, d mo: - than the 36 known events derived from the operators' logs.

Question Does the static relay panel have adequate surge protection to withstand the effects of a 500 kv fault?

l{c_gonse The panel has surge protection on a!I of its external interfaces. These interfaces include current and potential transformer inputs from the 500 kv circuits, the DC power control source, and the control outputs to operate the breakers. No failures have occurred close to the surge protection interfaces, therefore, there is no indication that the surge protection is inadequate.

The transistor that failed was not directly connected to an outside interface. The card on which this transistor was installed is sheltered from outside influences by other similar cards.

The input and output signals for the timing circuit card go through other similar cards containing the same model transistor. None of the other transistors failed during the loss of offsite power event. The failed transistor is one of nine identical transistors on the timing circuit card. Nthough some of the other transistors on the card were more electrically exposed than the failed transistor, they did not fail. Therefore,.the failed transistor was shown to be adequately protected from the fault current surge because it was less electrically exposed than other identical transistors. Therefore, the transistor failure was not caused by the fault and is determined to be a random failure.

2