GPU Nuclear Corporation i L:
E3 yi Post Office Box 480 d
M
=
Route 441 South Middletown. Pennsylvania 17057 717 944-7621 TELEX 84-2386 Writer's Direct Dial Number:
October 25, 1982 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mailstop P-428 Washington, D.C.
20555
Dear Mr. Denton:
Subject:
Status of Restart Items - TMI Unit 1 Order and Notice of Hearing Dated August 9, 1979 - Docket No. 50-289 is a summary status report for items that must be certified by the NRC staff prior to restart as a result of the NRC Order and Notice of Hearing dated August 9,1979. is for items that the NRC must verify are complete to fulfill various restart commitments other than those relating to the August 9,1979 Order.
The data for GPUNC is current as of October 15, 1982. We did not have data of equivalent timing for the NRC status on verification of these items, but will provide it when we have it available in future status l
summaries.
l Very truly yours, l
~
R. C. Arnold l
President k
Enc.
90(g cc:
J. F. Stolz, Chief of Operating Reactors Branch 4 R. C. Hay..as, Regional Administrator Region 1 GPil Nociaar Onrnoration is a subsidiary of the General Public Utilities Corporation l
8210290204 821025 i
PDR ADOCK 05000289 l
P PDR
2 TMI-1 8/9/79 ORDER CERTIFICATION STATUS
SUMMARY
TOTAL ITEMS TOTAL ITEMS FOR GPUNC TO COMPLETE 128 FOR NRC CERTIFICATION 129(3)
COMPLETED AS OF 10/15 97 COMPLETED AS OF 9/17 65 SCHEDULED FOR OCT, 3
(N0 UPDATE OBTAINED)
SCHEDULED FOR N0v.
11 SCHEDULED FOR DEC.
6 SCHEDULED FOR JAN.
0 SCHEDULED FOR FEB.Cl) 6 SCHEDULED FOR MAR.( )
5 (1)
MUST BE DONE DURING HOT FUNCTIONAL IESTING.
(2)
MUST BE DONE DURING POWER ESCALATION IESTING.
(3)
LOCAL SCHOOL'S EMERGENCY PLAN - COMPLETE NOT BEING TRACKED THROUGH G0UNC.
BASED ON GPUN UNDERSTANDING THAT ITEMS IIH AND III ARE COMPLETED.
ENCLOSURE 1
TMI-1 RESTART. STATUS
SUMMARY
(NON-CERTIFICATION) i TOTAL ITEMS TOTAL ITEMS FOR GPUNC TO COMPLETE 93 FOR NRC INSPECTION (AS OF 10/15)
COMPLETED AS OF 10/15 47 NO UPDATE OBTAINED SINCE GPUN AND SCHEDULED FOR OCT.
14 NRC HAVE NOT AGREED UPON A BASE LIST
^
SCHEDULED FOR N0v. e 17 SCHEDULED FOR DEC.
9 SCHEDULED FOR JAN.
1 SCHEDULED FOR FEB.(1) 2 SCHEDULED FOR MAR.
3 (1)
MuST BE DONE DURING HOT FUNCTIONAL IESTING.
(2)
MUST BE DONE DURING POWER ESCALATION IESTING.
9