Provides Supplemental Response to NRC Ltr Re Violations Noted in IE Insp Repts 50-259/82-10,50-260/82-10 & 50-296/82-10.Div of Procedures Manual N82A3 Will Not Be Revised Until 821001 Due to Scope of Effort Involved
ML20065N260
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 08/18/1982
From: Mills L
TENNESSEE VALLEY AUTHORITY
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 8210220151
Download: ML20065N260 (1)


Text

.

TENNESSEE 'V' ALLEY AUTHORITY CH#.TTANOdGA, IENNESSEE 37401 400 Chestnut Street Tower II 32 IJ!r; 26 AB: 3 1 August 18, 1982 U.S. Nuclear Regulatory Commission I

Region II ATTN: James P. O'Reilly, Regional Administrator 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303

Dear Mr. O'Reilly:

In my June 10,1982. letter to you, we provided our response to Browns Ferry Inspection Report Nos. 50-259/82-10, -260/82-10, and

-296/82-10. In our response to Violation Item B, we indicated that a revision to Division Procedures Manual (DPM) N82A3, Compliance Management, would be issued by August 15, 1982. As discussed with F. Cantrell of your staff on August 13, 1982, we will not be able to revise DPM N82A3 until October I, 1982 because of the scope of the-effort involved. If you have any questions, please call Jim Domer at FTS 858-2725.

i To the best of my knowledge, I declare the statements contained herein are complete and true.

Very truly yours, TENNESSEE VALLEY AUTHORITY L. M. Mills, Manager Nuclear Licensing l

I210220151 820818 DG 05000 An Equal Opportunity Employer

.-