Completes Response to IE Bulletin 30-06, ESF Reset Controls. Review of Actions Taken in Compliance W/Bulletin Revealed Deficiencies in Temporary Procedure 81-6A Re Valve Testing.New Test Procedures Developed
ML20065L796
Person / Time
Site: Pilgrim
Issue date: 10/07/1982
From: Morisi A
BOSTON EDISON CO.
To: Haynes R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
REF-SSINS-6820 82-266, IEB-80-06, IEB-80-6, NUDOCS 8210190721
Download: ML20065L796 (2)


Text

wr 9.

BomTAN EDISON COMPANY orwenac arricco son savtefou starry SoSfoN MAasACHug TTE03199 A. V. M O RISI l

MANAGER f

NUCLEAR OPERATIONS SUPPORT DEFh4TMENT October 7,1982 BECo. Ltr. #82-266 l

Mr. Ronald C. Haynes, Director Office of Inspection and Enforcement Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA.

19406 License No. DPR-35 Docket No. 50-293

Subject:

IE Bulletin 80-06 Reference (A). Boston Edison Letter dated June 27, 1980 from Mr. G. Carl Andognini to Mr. Boyce H. Grier (B): LER 82-025/01T-0

Dear Sir:

i In.the second response contained in Reference (A), Bo-ton Edison committed to complete IE Bulletin 80-06 related surveillance testing prior to start-up from Refueling Outage #5 (RF0 5). At start-up from RF0 5 we believed this commit-ment had been fully satisfied.

However, after Pilgrim returned to service an additional review was conducted i

to ensure the adecuacy and completeness of the Bulletin 80-06 tests. This re-view determined that a modified station surveillance procedure, Temporary l

Proced_ure 81-64, PCIS Valve Testing (TP81-64) had the following inadequacies:

(1) it inadvertantly overlooked the testing of the H2 Analyzer Isolation Valves; l

(2) it did not identify the individual Standby Gas Treatment System Isolation

(

Valves; (3) it incorrectly indicated that the 02 Analyzer Valves are closed after i

reset, when the valves are actually open.

To correct the identified inadequacies, the Operations Review Comittee approved two new temporary procedures, TP82-38, Balance of Plant isolation "A" and TP82-39,

(

Balance of Plant Isolation "B". During the unscheduled shutdown commencing August 13, 1982, th ! additional testing was conducted.

This cesting revealed that wiring l

to the H2 Analyzer valves was incorrect. We developed and' implemented corrective i

actions, developed appropriate new test procedures and conducted a test of the logic.

L The logic tested consistent with its wiring schemes, satisfactorily concluding this

~

t test.

LER 82-025/01T-0 has been issued to satisfy reporting requirements.