Forwards Suppl 3 to BAW-2127, Plant-Specific Analysis in Response to NRC Bulletin 88-011, 'Pressurizer Surge Line Thermal Stratification' Davis-Besse Nuclear Power Station Unit 1
ML20065D054
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 03/30/1994
From: Shelton D
CENTERIOR ENERGY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20065D057 List:
References
2215, IEB-88-011, IEB-88-11, NUDOCS 9404060193
Download: ML20065D054 (2)


Text

-y  ;, -- - W w:

' C L- s g-y ,

-. , CENTERROR .

.  % ENERGY n i a

6200 Oak Tree Boulevard Mail Address: . Donald C. Shelton d independenceOH' P.O. Box 94661 Senior Vice President !

Clevelond.0H 441014661 Nuclear g 216-447-3153 y ,

Fox 216 447-3123 '

5 g 'f I

Docket Number 50-346 ~!

License Number NPF-3 .!

b Serial Number 2215 ,

7 March 30, 1994 9

4  ;

' United States Nuclear Regulatory Commission i

-Document Control Desk Washington, D. C. 20555  ;

i Subj ec t : Submittal of BAV-2127, Supplement 3, Plant-Specific' Analysis in Response to NRC Bulletin 88-11, Pressurizer Surge Line .,

Thermal Stratification, for the Davis-Besse Nuclear Power 1 Station

. Gentlemen: }:

.]

The purpose of this letter is to submit BAV-2127, Supplement 3,--

" Plant-Specific Analysis in Response to NRC Bulletin 88-11, Pressurizer. ,

Surge Line Thermal Stratification," for the Davis-Besse Nuclear Power

' Station (DBNPS). Toledo Edison's letter dated December 3, 1993 (Serial '

  • s -Number 2190) provided the current status and Toledo Edison's schedule i for completion of the remaining actions to resolve Bulletin 88-11 for

'the DBNPS.

The enclosed report, BAV-2127, Supplement 3, " Plant Specific Analysis

.in Response to NRC Bulletin 88-11, Pressurizer Surge.Line Thermal-5 <*1fication," provides a revised plant-specific analysis-for the

-!N .S. 'The report supersedes in its entirety BAV-2127, Supplement 1, 1 G1ch was previously submitted _(Serial Number 1982, dated October 8, a

1991). The report'shows that stresses for~the surge line: pressure i

boundary components-remain within allovable limits-and that accumulated

fatigue' usage vill satisfy the applicable-code requirements.and~

l regulatory commitments for -the 40-year licensed life: of the DBNPS. _

This' report was predicated on the assumption that certain modifications 46 4

G PDR- n# 3

)

. opero+ing companiesn c! eve:cnd Doctne muminating U

Toleao Edison --

1' O

rm. 1

i. '

- r , t

' Docket Number 50-346 License Number NPF-3 Serial Number 2215

'Page 2

.to pressurizer' surge line'vhip restraints and a spring support:and upgrading of insulation vould be completed during the Ninth Refueling Outage (9RFO). _The 9RF0 is currently scheduled to commence on

.0ctober 1, 1994.

Should you have any questions or' require additional information, please contact Mr. Villiam T, O'Connor, Manager - Regulatory Affairs, at (419) 249-2366.

V truly yours,

/dhb - -

AKZ/cfb ^ DC S cc: J. B. Martin, Regional Administrator, NRC Region III S. Stasek, DB-1 NRC Senior Resident Inspector G. Vest, Jr., DB-1 NRC/NRR Project Manager Utility Radiological Safety Board 1

.$