Forwards Rev of Info Submitted on 931229 Re Actions to Resolve NRC Bulletin 93-003, Resolution of Issues Related to Reactor Water Level Instrumentation in Bwrs
ML20065B932
Person / Time
Site: Monticello 
Issue date: 03/31/1994
From: Richard Anderson
NORTHERN STATES POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
IEB-93-003, IEB-93-3, NUDOCS 9404040212
Download: ML20065B932 (3)


Text

-.

4 Northem States Power Company 414 Nicollet Mall Minneapolis, Minnesota 55401-1927 Telephone (612) 330-5500 March 31, 1994 10 CFR Part 50 Section 50.54(f)

U S Nuclear Regulatory Commission Attnt Document Control Desk Washington, DC 20555 MONTICELLO NUCLEAR GENERATING PLANT Docket No. 50-263 License No. DPR-22 Revision of Information Submitted on December 29, 1993 Concerning Actions to Resolve NRC Bulletin 93-03: Resolution pf Issues Related to peactor Water Level Instrumentation in BWRs The purpose of this letter is to inform you of a change in our plans, as previously described in our letter dated December 29, 1993, concerning the actions we are taking to resolve the issues identified in NRC Bulletin 93-03,

" Resolution of Isuues Related to Reactor Water Level Instrumentation in BWRs".

In our December 29, 1993 letter we indicated that as a result of technical issues encountered while preparing the backfill modification, we intended to take a phased approach when implementing the new system until such time as we were confident that the backfill system was performing as intended with no adverue impact on the accuracy or reliability of the reactor water level instrumentation.

It was anticipated that at least one full operat...g cycle j

would be needed to assess system performance through the various plant transients and environmental conditions that might be encountered.

As a result of subsequent discussions with the NRC staff on this issue, and in j

recognition of the staff's desire to have a resolution for Bulletin 93-03 implemented at all BWRs in an expeditious manner, we have reviewed our plans for trial implementation and on-line performance monitoring of the new backfill system.

Although we would prefer a longer term trial and monitoring period to confirm that the backfill system was performing as intended, we consider that our most significant technical concerns could be adequately addressed by an abbreviated (30 day maximum) trial period.

i We are therefore revising the commitment contained in our December 29, 1993 letter as follows-By the end of the first cold shutdown occurring after December 31, 1993, we will commence injection, on a trial basis, into one safeguards reference leg and one fuel zone reference ler (both sharing a common vessel nozzle) for a maximum period of 30 days.

If, at the end of that j

time, it is determined that the system is performing satisfactorily with no adverse impact on the accuracy or reliability of the water level I

gi r

9404040212 940331 ADOCK0500ggg3 PDR Q

9 e

USNRc NORTHERN STATES POWER COMPANY March 31, 1994 Page 2 instrumentation, we will commence injection into the remaining safeguards and fuel zone reference legs.

This letter is being provided to appraise you of our change in plans and commitments concerning implementation of the backfill modification.

Although we would welcome any feedback you may wish to provide, no specific reply is necessary.

Please contact Terry Coss, Sr Licensing Engineer, at (612) 295-1449 if you require any additional information concerning this submittal.

j f

W Roger O Andersor.

Director Licensing and Management Issues cc: Regional Administrator-III, NRC NRR Project Manager, NRC Resident Inspector, NRC State of Minnesota, Attna Kris Sanda J Silberg

Attachment:

Affidavit to the US Nuclear Regulatory Commission l

i

+.

o' g

c>

UNITED STATES NUCLEAR REGULATORY COMMISSION NORTHERN STATES POWER COMPANY MONTICELLO NUCLEAR GENERATING PLANT DOCKET NO. 50-263 Revision of Information Submitted on December 29, 1993 Concerning Actions to Resolve NRC Bulletin 93-03: Resolution of Lpoues Re_ Lated to Reactor Water Level Inst Gmentation in BWRs Northern States Power Company, a Minnesota corporation, hereby provides a revision to the information requested by NRC Bulletin 93-03: Resolution of Issues Related to Reactor Water Level Instrumentation in BWRs.

This letter contains no restricted or other defense information.

NORTHERN TATES POWER CO PANY

/#f/

By / [ ger o Anderso'n Director Licensing and Management Issues f

' before me a notary public in and On this 3 ay of for said County, personafly appeared Roger O Anderson, Director, Licensing and Management Issues, and being first duly sworn acknowledged that he is authorized to execute this document on behalf of Northern States Power Company, that he knows the contents thereof, and that to the best of his knowledge, information, and belief the statements made in it are true an that it is not interposed for delay.

s

--.3......._............._.....,_

MEM NOTARYpW04mNNE90TA HM COUNTY MyCosimiselse Euphe kn.31,2000 weWWW4%%WMAWWWWWW%4s yI--*p<

grr-9m