Documents 820830 Discussions Re Personnel Changes Per FSAR, SER & Tech Specs at Facility.Expeditious NRC Review Requested
ML20064N004
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 08/30/1982
From: Schroeder C
COMMONWEALTH EDISON CO.
To: Schwencer A
Office of Nuclear Reactor Regulation
References
4849N, NUDOCS 8209080194
Download: ML20064N004 (3)


Text

_ _ _ _ _ _ _ _ _

  • ~

/"2D Commonwealth Edison

(

) one First National Pir2a, Chicigo, Illinois

( O 7 Addr:ss R: ply to: Post Offics Box 767 j Chicago, Illinois 60690 l

Augus t 30, 1982 Mr. A. Schwencer, Chief Licensing Branch #2 Division of Licensing j

U. S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

LaSalle County Station Units 1 and 2 Personnel Changes NRC Docket Nos. 50-373' and 50-374 References (a):

LSCS FSAR Sechon 13.1.3.1.

(b):

LSCS SER Section 13.1.

(c):

ANSI N18.1-19 71.

(d):

LSCS Technical Specifications Section 6.1.D.

(e):

LSCS Technical Specifications Figure 6.1-2.

Dear Mr. Schwencer,

The purpose of this letter is to document discussions today between Dr. A. Bournia and Mr.

G. Rivenbark of your staf f and C. W.

Schroeder o f Commonwealth Edison.

Commonwealth Edison Company is considering certain personnel changes at LaSalle County Station.

Included in these changes is the need to fill the position of Assistant Superintendent, Operations, which will be vacated due to promotion of the incumbant to the position of Superintendent.

A review of the pertinent documentation reveals the following regarding the requirementa for the individual holding the position of Assistant Superintendent, Operations:

1.

Reference (a) commits LSCS to ANSI N18.1-1971, lists plant staf f positions and designates ANSI N18.1-1971 equivalent titles.

Fo r the position of Assistant Superintendent, the ANSI equivalent is Assistant Plant Manager.

2.

Reference (b) states that the NRC has "... reviewed the qualification requirements described in Section 13.1 of the Final. Safety Analysis Report and find they meet those hO l qualifications described in American National Standards 0

In stitute N18.1-19 71..."

khg9080194820830 ADOCK 05000373 p

PDR

A. Schwencer August 30, 1982 3.

- A review o f Reference (c), Section 4.2.1 Plant Managers, indicates that "The plant manager shall have acquired the experience and equivalent training normally required to be eligible for a Senior Reactor Operator's license whether or not the examination is taken."

Section 4.2.2, Operations Manager, states "....the operations manager shall ~ hold a' Senior Reactor Operator's license...."

4.

Reference (d) states that " Qualifications of the station management and operating staf f shall meet acceptable levels as described in ANSI N18.1-19 71...."

5.

Reference (e) indicates that the Operating Assistant Superintendent requires a Senior Reactor Operator's license.

It is Commonwealth Edison's position that the position of Operating Assistant Superintendent does correspond to the ANSI N18.1-1971 position of Assistant Plant Manager, as committed to in Reference (a) and approved by the NRC in Reference (b).

As such, it is our position-that the individual fulfilling this position should NOT be required to hold a current SR0 on LSCS.

It is Commonwealth Edison's understanding that the staf f l

currently views the position of Operating Assistant Superintendent as fulfilling the ANSI position of' Operations Manager and thus requiring a current SRO license.

The individual being considered for this-position at LSCS has been employed by Commonwealth Edison for over 15 years.

He has held an SRO license on Dresden Nuclear Power Station and has held many positions at Commowealth Edison stations including:

Tech Staf f Supervisor (Technical Manager)

Operating Engineer (Operations Manager)

Operating Assistant. Superintendent ( Assistant Plant Manager)

In order to allow this highly qualified individual to assume the position of Operating Assistant Superintendent at LSCS, the following agreement is proposed:

"An individual who meets the requirements of ANSI N18.1 -19 71, for the ANSI positions of Plant Manager and Operations manager, with the sole exception that he does not hold a current SRO license on LSCS, will be allowed to assume the position of Operating Assistant Superintendeat; providing a)

He sits for the SRO examination at LSCS no later than the first opportunity af ter six months following his appointment to the position.

b)

Operating decisions made by this individual prior to his holding a current SRO at LSCS shall be approved by, or directed through, individuals (s) holding a current SRO license at LSCS."

A. Schwencer Augus t 30, 1982 Due to the desire of Commonwealth Edison to immediately appoint an individual to this position, your expeditious review is appreciated, If there are any further questions in this matter, please contact this office.

Very truly yours, CWdkJ~ but C. W. Schroeder Nuclear Licensing Administrator 1m 4898N