Responds to NRC Re Violations Noted in IE Insp Rept 50-271/82-08.Corrective Actions:Nuclear Safety Audit & Review Committee Will Review Safety Evaluations for Design Changes & Procedures Will Be Revised by 820901
ML20064M610
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 08/12/1982
From: Heider L
VERMONT YANKEE NUCLEAR POWER CORP.
To: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20064M603 List:
References
FVY-82-88, NUDOCS 8209080044
Download: ML20064M610 (2)


Text

NRMONT YANKEE NUCLEAR POWER CORPORATION 2.C.2.11 FVY 82-88 RD 5, Box 169, Ferry Road, Brattleboro, VT 05301 g

ENGINEERING OFFICE August 12, 1982 1671 WORCESTER ROAD FRAMINGHAM MASSACHUSETTS 01701 TELEPHONE 617-872-8100 United States Nuclear Regulatory Commission Office of Inspection and Enforcement Region I 631 Park Avenue King of Prussia, PA 19406 Attention:

Richard W. Starostecki, Director Division of Project and Resident Programs

References:

(a) License No. DFR-28 (Docket No. 50-271)

(b) USNRC Letter to USNRC, dated July 15, 1982; Inspection Report 50-271/82-08

Subject:

Response to I&E Inspection No. 50-271/82-08

Dear Sir:

This letter is written in response to Reference (b) which indicates that one of our activities was not conducted in full compliance with Nuclear Regulatory Commission requirements.

The alleged violation was identiffeJ during the inspection performed by your Mr. W. J. Raymond during the period May 11 - May 31,1982.

Information is submitted as follows in answer to the alleged violations documented in Appendix A to your letter:

Violation Technical Specification 6.2.B establishes the requirerents (82-08-03) governing the function and responsibilities of the Nuclear Safety Audit and Review Committee (NSARC) and requires under paragraph 6.2.B.5.c that the Committee review the safety evaluations for changes made to plant equipment or systems completed under the provisions of 10CFR50.59.

Contrary to the above, as of May 28, 1982, the Safety evaluations for twelve design changes to plant equipment / system, completed in 1981 and reported to the NRC in the 1981 Annual Report, has not been reviewed by the NSARC.

Response

The NSAR Chairman has reviewed the Status Log of Plant Design Change Requests (PDCR's) which have been initiated since 1980, to determine those PDCR's which have been approved for implementation. All approved PDCR's which have not been reviewed will be issued for review by the NSAR Committee by the end of August. The Committee will review the safety evaluations for changes to equiprent or systems completed under the provisions of 8209080044 820830 gDRADOCK 05000271 PDR

VERMONT YANKEE NUCLEAR POWEH CORPORATION United States Nuclear Regulatory Commission August 12, 1982 Attention:

Mr. R. W. Starowstecki Page 2 10CFR50.59 to verify that such actions do not constitute unreviewed safety questions. This review function will be finalized at the next regularly scheduled NSAR meeting.

In order to prevent future violations of this nature, we have reviewed the procedures and instructions which provide for the distribution of approved PDCR's to NSAR Committee. Changes will be made, as necessary, to ensure proper distribution of these documents to the Committee; these changes will be completed by September 1, 1982.

We trust that this response is satisfactory; however, should additional information be required, please contract us.

Very truly yours, VERMONT YANKEE NUCLEAR POWER CORPORATION L. H. Heider Vice President