Forwards Reactor Containment Bldg Integrated Leak Rate Test Sequoyah Nuclear Plant Unit 1 Conducted 941217-20. As-Found & as-left Acceptance Criteria Is 0.1875% Per Day
ML20064M075
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 03/21/1994
From: Powers K
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20064M078 List:
References
NUDOCS 9403280094
Download: ML20064M075 (3)


Text

.

t '

i +

f k

Tennessee va ey vou rou cese su ma sa;av na+y Ten ecee 3r379 n

March 21, 1994 l

1 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:

In the Matter of

)

Docket No. 50-327 Tennessee Valley Authority

)

SEQUOYAll NUCLEAR PLANT (SQN) - UNIT 1 - REACTOR CONTAINMENT BUILDING INTEGRATED LEAK RATE TEST (CILRT)

Enclosed is the summary technical report on the CILRT for SQN Unit 1 conducted December 17-20, 1993. This report is being submitted for your review in accordance with 10 CFR 50, Appendix J Sections V.B.1 and V.B.3.

The "as-found" and "as-left" acceptance criteria is 0.1875 percent per i

day.

The reportable as-found mass lerk rate for the CILRT was 0.1980 percent per day and was attributed to the breakage of 0-ring seals on Penetration X-79B that occurred during replacement of the penetration flange approximately two weeks before the conduct of the CILRT.. The reportable as-left leak rate was 0.1306 percent per day.

)

Please direct questions concerning this issue to D. V. Goodin at (615) 843-7734.

Sincerely l

6 Ken Powers Site Vice President Sequoyah Nuclear Plant Enclosure

/

1 cc:

See page 2

/

p5 j

)

j i

J 250008 94032800,4 94o321 PDR ADOCK 05000327 P

PDR((

j

.~

U.S. Nuclear Regulatory Commission Page 2 March 21, 1994 cc (Enclosure).

Mr. D. E. LaBarge, Project Manager U.S. Nuclear Regulatory Commission One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 NRC Resident Inspector Sequoyah Nuclear Plant i

2600 Igou Ferry Road Soddy-Daisy, Tennessee 37379-3624 Regional Administrator U.S. Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323-2711 L

e 4

4 4

1 m

l I

ENCLOSURE SEQUOYAH NUCLEAR PLANT UNIT 1 REACTOR BUILDING CONTAINMENT INTEGRATED LEAK RATE TEST CONDUCTED DECEMBER 17-20, 1993 (S57 940309 890)

_