Interim Deficiency Rept Re Lack of Procedural Qualification for Pipe Bends.Initially Reported on 821109.Rev to Procedure MCP-7 to Be Completed by 830211.Requalification Effort to Be Conducted After Issuance of Rev
ML20064L800
Person / Time
Site: Zimmer
Issue date: 02/04/1983
From: Borgmann E
CINCINNATI GAS & ELECTRIC CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, QA-2250, NUDOCS 8302150377
Download: ML20064L800 (2)


Text

4-Y

=....,

THE CINCINNATI GAS & ELECTRIC COMPANY WM. H. ZIMMER NUCLEAR POWER STATION, UNIT 1 P.O. BOX 201, MOSCOW, OH 45153 February 4, 1983 QA-2250 E. A. B ORG M AN N stwsom vict PatssotNT U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137 Attention:

Mr. J. G. Keppler Regional Administrator RE:

WM. H. ZIMMER NUCLEAR POWER STATION UNIT 1 10CFR50.55(e) ITEM M-67, LACK OF PROCEDURAL QUALIFICATION FOR PIPE BENDS, DOCFET NO.

50-358, CONSTRUCTION PERMIT NO. CPPR-88 W.O. 57300, JOB E-5590, FILE NO. NRC-8 Gentlemen:

This letter constitutes an interim report concerning the subject condition, initially reported to the Commission on November 9, 1982, as a potentially reportable deficiency under the requirements of 10CFR50.55(e).

As stated in our previous report, QA-2152, dated December 8, 1982, efforts were underway to requalify pipe bends performed in the field of small bore piping by January 31, 1983. This requalification require-ment mandated changes to H. J. Kaiser Company (HJK) Procedure MCP-7,

" Piping Installation." However, several other parameters have been incor-porated into the procedure, resulting in a lengthy review process. This revision is expected to be completed no later than February ll, 1983.

The requalification effort will be conducted immediately after the issu-ance of this revision, however, some material is not available. A follow-up report detailing the requalification results for the available pipe will be submitted by February 28, 1983.

With regards to the date of this report, per the February 1,1983 telephone conversation between Mr. P. F. Warnick of the NRC and Mr. H. R.

Sager of CG&E, the committed submittal date of this report (continued) 8302150377 830204 PDR ADOCK 05000358 FEB 7 1988 S

PDR

1-

  • :[

Mr. J. G. Keppler Regional Administrator Region III February 4, 1983 QA-2250 Page 2 was revised-from' January 31, 1983, to February 4, 1983.

We trust the above will be found acceptable as an interim report under 10CFR50.55(e).

Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY

~

By -

E. A. BORGMANN SENIOR VICE PRESIDENT FKP:plc cc: NRC Office of Inspection & Enforcement Washington, D.C.

20555 NRC Senior Resident Inspector Attn:

W. F. Christianson Zimmer Project Inspector Region III i