"RTELEDYNE ENGNEERING SEFNICES 130 SECOND AVENUE WALTH AM, M ASSACHUSETTS 02254 t617) 830-3350 TWx (710) 324-7580 7
'>g - k February 11, 1983 5633-43 Mr. Harold Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, Maryland 20114
Subject:
Independent Design Review for the Shoreham Nuclear Power Station
Dear Mr. Denton:
TES has completed our preliminary review which has resulted in the issuance of 16 Findings.
As noted in TES letter 5633-20 dated November 2,1982, these Findings should be considered Preliminary until a response is received from LILC0 and review of those responses is conducted by TES.
To date TES has 11 responses from LILC0 and these are being reviewed.
The review of responses to Findings is being carried out as follows:
1.
The initiator of the original RRF reviews the LILC0 response and submits the results of that review on a RRF-ICR form.
2.
The Project Manager and the Chairman of the Internal Review Committee meet with the reviewer, and any other members of the IDR Project Team they feel are required, to discuss the results of the review of LILC0 responses.
3.
The Project Manager and the Chairman of the Internal Review Committee must reach agreement on the final classification of each item.
The reasons for their conclusions will be set forth in writing, signed and attached to the original ICR.
In the process of reviewing LILC0 responses, telephone conversations and/or meetings between TES, LILC0 and Stone and Webster will be necessary.
Records of these conversations and meetings will be made by TES and transmitted to LILC0 and the NRC.
'9[A G302150235 830211
(
. h* %
Lp.
[DRADOCK 05000322 PDR ENGINEERS AND METALLURGISTS m
'RTELEDYNE ENGINEERING SERVICES Mr. Dentc1 (USNRC) 5633-43 February 11, 1983 Page 2 If you have any questions please do not hesitate to contact James P.
King or the writer.
Very truly yours, TELEDYNE ENGINEERING SERVICES her>zs/d Y Ynck Donald F. Landers Senior Vice-President DFL/lh cc: