Monthly Oper Rept for Nov 1978
ML20064H608
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 12/01/1978
From: Hairston W
ALABAMA POWER CO.
To:
Shared Package
ML20064H606 List:
References
NUDOCS 7812210212
Download: ML20064H608 (4)


Text

.

JOSEPH M. FARLEY NUCLEAR PLAh"I UNIT 1 NARRATIVE

SUMMARY

OF OPERATIONS November, 1978 The unit was operated at 100% power during November with no unit shutdowns or significant power reductions.

The following significant safety related maintenance was performed in November:

1. Reworked 1C charging pump motor mount frame, replaced bearings in speed increaser, and realigned pump. The 1C charging pump is now operable.
2. Rebuilt 2C diesel generator B air compressor.
3. Repaired 1B boron injection tank recirculation pump seal.
4. Replaced R-11/R-12, containment atmosphere particulate / gaseous radioactivity monitoring system, vacuum pump / motor and low flow relay.
5. Repaired LS-511, river water A train auto-start pond level switch.
6. Repaired circuit ET-7B, heat tracing on boron injection tank inlet valve.
7. Pulled river water pump 10 after indication of '

high vibration. Flushed the lube and cooling piping for the A and B-train water pumps. Vibration problems were also experienced on river water pumps 4 and 9. Motor rework was begun on river water pump 7 after the motor apparently seized.

781231cq,qy

( OPERATING DATA REPORT DOCKET NO. 50-348 DATE 12-1-lo COMPLETED ltY W. G. Hairsten, III TELEPHONE (?o;Tc01-5156 OPERATING STATUS

1. Unit Name: Joseph M. Farley Unit 1 Notes 1/ Since 12-1-77-date November, 1973 of co:r::::ercial operation.
2. Reporting Period:
3. Licensed Thermal Power (MWt):
4. Nameplate Rating (Gross MWe): 860 ,
5. Design Electrical Rating (Net MWe): 829 .
6. Maximum Dependable Capacity (Gross MWe): ' Mo*
7. Maximum Dependable Capacity (Net MWe):
8. If Changes Occur in Capacity Racings (Items Number 3 Through 7) Since Last Report. Give Reasons:

N/A

9. Power Level To Which Restricted,If Any (Net MWe): N/A
10. Reasons For Restrictions. If Any: N/A

(- *. This Month Yr to.Date Cumulative

11. Hours In Reporting Period 720 8016 8760
12. Number Of Hours Reactar Was Critical 720 -7003.3 7546.6 u 850.6
13. Reactor Reserve Shutdo vn Hours 960.7
14. Hours Generator On Line 720 6892.9 7404.7
15. Unit Reserve Shutdown Hours 0 0 0
16. Cross Thermal Energy Cenerated (MWH) 1.896,861 17',731,952 19,035,955 .
17. Gross Electrical Energy Generated (MWH) 610,874 5,679,464 6,100,850 IS. Net Electrical Energy Generated (MWH) 581.888 5,375,770 5,771,700
19. Unit Service Factor 100% d6.u7 84.5 %
20. Unit Availability Factor 100% 86.0% 84.5 %
21. Unit Capacity Factor (Using MDC Net) 97.5% 80.9% 79.5%
22. Unit Capacity Factor (Uning DER Net) 97 5% 80.9% 79.5%
23. Unit Forced Outage Rate 0% 6.6% 7,9;
24. Shutdowns Scheduled Over Next 6 MonthsIType.Date, and Duration of Eachi:

Refueling, Feburary, 1979, 8 weeks

25. If Shut Down At End Of Report Period. Estimated Date of Startup: N/A .
26. Units In Test Status (Prior to Commercial Operationi: Forecast Achieved INITIAL CRITICALITY 0~0' ~

~

INITIAL ELECTRICITY - e

~

  • COMMERCI AL Ol'ERATION 12-1-77 12-1-72 The Nameplate Rating / Design Electrical Rating will be used for the Maximum Dependable experience. Capacity until an accurate value can be determined from operating (9/77 )

t AVERACT DAILY UNIT POWER LEVEL DOCKET NO.

50-348 WIT Farley Unit 1 DATE 12-1-78 COMPLETED BY W. G. Hairston, III TELEPHONE (205) 899-5156 310 NTH November DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (31We Net) (31We-Net) 1 817 37 782

- 819 748

~ -3 IS 819 796 3 ,,

817 805 4

813 813 5 21 .

807 812 6 22 7

799 811 23 g 816 803 9 821 25 820 816 10 ii 812 .

811 .

805 811

,g g3 817 , 810 34 811 807 30 I5 810 3 N/A 16 811 INSTRL'CTIONS Oa thi> format !ist the average daily unit power level in S!We Net for each day in the reporting month. Compute to the nearest whole megawatt.

(9/77)

O tJNII SilU1 DOWNS AND POWER REDUC 110NS I

fNAIE ty Unit 1 DATE 12-1-/8 COMPT EIFD Igy .W. C. 15irsto REPORT MONTil November

' LEPlONE (205) 8 W 5T$8i' jII e.

c-

.$ ~ 3 Yk Licensee jg f%

n?

Cause & Corresa ne No - Date ~E>

4 :E5 Event  ? At:4on to S 2s cE 3e Itepost c uTC !0 v

Pievent itetunente

{

O There were no unit shutdowns or significant power reductions during November, 1978.

1 2 3 4 IS Forced Reason: Method: Exhibii G - Instinctions S: Scheduled A.I'quipment Failure (Esplain) 1 Manual for Preparation of Data I 114f aintenance ci Tes 2 Manual Scram. Entry Sheets for Licenwe I C Rcruel.ng 3 Autonutie Scram. Eveni Reposi (LI RIl' ele (NtlRI G-i D Regulator) Ressaiction 4-Other (Explain) 01611 j 1:-Operator Traming & Licenw Examination j F Atinunistrative 5

. G Operational 1:sros (Explain) Estubis 1 - Same Somcc I Il4);hes (l:splain t l'8/77)