ML20064E533
| ML20064E533 | |
| Person / Time | |
|---|---|
| Site: | Zimmer |
| Issue date: | 12/17/1982 |
| From: | Borgmann E CINCINNATI GAS & ELECTRIC CO. |
| To: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| References | |
| 10CFR-050.55E, 10CFR-50.55E, QA-2167, NUDOCS 8301060045 | |
| Download: ML20064E533 (2) | |
Text
r o
~
_ [h.,. =
THE CINCINNATI GAS & ELECTRIC COMPANY sg ZIMMER NUCLEAR POWER STATION P.O. BOX 201 MOSCOW, OH 45153 CINCINNATl, OHIO 45204 December 17, 1982 QA-2167 E. A. BoRG MAN N SENrOR VtCE PRESIDENT U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137 Attention:
Mr. J. G. Keppler Regional Administrator RE:
WM. H. ZIMMER NUCLEAR POWER STATION UNIT 1 10CFR50.55(e) ITEM E-20 CABLE TRAY HANGER INSPECTIONS DOCKET NO. 50-358, CONSTRUCTION PERMIT NO. CPPR-88 W.O. 57300 JOB E-5590 FILE NO. NRC-7 E-20 Gentlemen:
Ihis letter constitutes an interim report concerning the subject condition reported under the requirements of 10CFR50.55(e).
Interim report, QA-1836, dated June 25, 1982, reported that a review of inspection records of electrical cable tray hangers on various elevations of the Auxiliary Building, revealed that inspections per-formed by some inspectors did not properly assess field welds for com-pliance with procedure requirements.
A Management Corrective Action Roquest was initiated for evalu-ation and assessment of electrical cable tray hanger inspections prev-iously performed. Evaluation and assessment of corrective action has been completed. Henry J. Kaiser Company (HJK), the principal constructor, will reinspect 100% of all accessible cable tray hanger field welds to the current requirements, except for those in the main control room, which will be inspected by CG6E to the current requirements. The rein-spection effort has been delayed due to clarified separation criteria given by Sargent & Lundy concerning electric separation. The reinspec-tion was expected to be completed by December 31, 1982, however, because of this delay, the reinspection is now expected to be completed by April 30, 1983, at which time a final report will be submitted.
8301060045 821217 EJ7 PDR ADOCK 05000358 ijgg 3 $$8 s
F~
Mr. J. G. Keppler Regional Administrator Region III December 17, 1982 QA-2167 Page 2 We trust the above will be found acceptable as an interim report under 10CFR50.55(e).
Yours very truly, THE CINCINNATI GAS & ELECTRIC COMPANY By E. A. BORGMANN SENIOR VICE PRESIDENT GNW:plc cc: NRC Office of Inspection & Enforcement Washington, D.C.
20555 NRC. Senior Resident Inspector Attn:
W. F. Christianson Zimmer Project Inspector Region III