ML20064D739

From kanterella
Jump to navigation Jump to search
Corrects Subj Rept Att to .Lpsi Pump Motor 2PM60A Was Not Inspec for Proper Bearing Installation.Pump Was Not Inspec Because It Has Been in Constant Oper Since Failure of 2PM60B & Would Have Failed by Now If Defective
ML20064D739
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 10/13/1978
From: David Williams
ARKANSAS POWER & LIGHT CO.
To: Seyfrit K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20064D742 List:
References
NUDOCS 7811080305
Download: ML20064D739 (1)


Text

_

f$lff

~

  • ~ -

-.-.....tw.

s L

. ARKANSAS P JWER & LIGHT COMPANY POST OFFIC5 BdX 551 ilTTLh AOCK. ARKANSAS 72203 (501) 3714000

. Fi"u.

,c O.ctober 13, 1978

..u.

2-108-5 t4r. K. V. Seyfrit, Director Office of Inspection G Enforcement U. S. Nuclear Regulatory Commission Region IV U,

i 611 Ryan Pla::a Drive, Suite 1000 i

Arlington, Texas 76011 4

i

Subject:

Arkansas N cI' ear on - Unit 2 Docket No

'0-363

~

License N

-o Significant Deficiency Report LPSI Pump Flotor Failure (Rev. 1)

(File: 2-0520)

Gentlemen:

We stated in the subject report, attached to our September 21, 1978, letter, that we had inspected LPS1 pump motor 2Ph!60A for proper bhar --

ing ins.allation. This was an error that was made because of an Tn-1; ternal n.iscommunication.

Pump motor 2PM60A was not inspected for!.I g

proper bearing installation.

-4 il t:2 3

l- :

q The decision not to inspect this motor was-based on the followi'ng 7

reasons:

.I

- 2PM60A had been in continuous operation following

=

the failure of 2PM60B.

~

- 2PM60A had been operating in all possibic modes such that if a bearing problem existed the pump would have aircady been destroyed.

We feel that the reasons listed above were sufficient for not inspecting the pump bearing.

A corrected report is attached.

Very truly yours,

~

Daniel 11. Williams Manager, Licensing DilW : CSP:vb 7 8110 8 De30'i Attachment p