I OUISIANA P O W E R & L I G H T! P O BOX 6008 *
,42octAnONoesta m NEW ORLEANS tOUISlANA 70174 * [504) 366-2345 USSIsESYt$
June 24, 1982 G. D. McLENDON Senior Vice President W3K-82-0367 Q-3-A35.07.34 Mr. John T. Collins, Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76012 SUBJ ECT:
Waterford SES Unit No. 3 Docket No. 50-382 Significant Construction Deficiency No. 34 "Buf f alo Forge HVAC Fan Shrouds" Third Interim Report
Reference:
- 1) LP&L Letter W3K-82-0254 to USNRC dated April 30, 1982
- 2) Telecon - L. Bass (LP&L) to L. Martin (USNRC) on June 22, 1982
Dear Mr. Collins:
In Reference ],
LP&L committed to submit a final report on the subject Significant Construction Deficiency by June 25, 1982. At the present time, the material to complete the work is on site and the material documentation is being processed. The systems associated with the fan shrouds have been turned over by the contractor to LP&L. We are now waiting for LP&L Start-up to assign a time frame in which the fan shrouds may be installed.
Based on the above restraint, it is anticipated that a final report will be submitted by September 15, 1982.
Very truly yours,
^
CDMcL/LLB/grf h
cc:
- 1) Director
/
I Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission j,{gggg\\/g Washington, D. C. 20555
- 2) Director 5L Office of Management
- Q'_ m28M Information and Program Control
. L. '
i U. S. Nuclear Regulatory Commission d
Washington, D. C. 20555
{
8207020192 820624 PDR ADOCK 05000382 S
PDR L
_