Text
.
9 l
THE CLEVELAND ELECTRIC ILLUMINATING COMPANY P.O. BOX 97 E
PERRY, OHIO 44081 E
TELEPHONE (216) 255L3737 S
ADDRESS-10 CENTER ROAD FROM CLEVELAND: 479 1260 m
TELEX: 241599 ANSWERBACK: CEIPRYo Serving The Best Location in the Nation PERRY NUCLEAR POWER PLANT January 27, 1994 PY-CEI/0 EPA-0194 L Brian Hall Ohio EPA Northeast District Office i
2110 E. Aurora Rd.
~
Twinsburg, Ohio 44087 Mr. Hall, This is a follow up to your telephone conversation on January 21, 1994, with Louise Barton (Environmental), and Jim Emley (Regulatory Affairs).
l As discussed, ve vill be taking advantage of the upcoming plant refueling outage to drain and inspect two of the plant water systems - service j
vater and circulating vater (which includes the condenser and cooling l
tover). In answer to your specific questions, the volume of circulating I
vater to be discharged is approximately 6.5 million gallons.
It vill be drained over a two to three day period scheduled to start February 16, 1994. Both water systems are scheduled to 'a returned to service on April 1, 1994.
If you have other questions or need more information, please contact Louise Barton at (216) 280-5512.
Sincerely, 7
Rob rt A. Stratman cc: IGC Project Manager IRC Resident Inspector Office NRC Document Control Desk l
NRC Region III
\\
9402030225 94o127 PDR P
ADOCK 0500044o 6p'1
) {
PDR y