o TENNESSEE VALLEY AUTHOR""
C M '. T P A NCOG A. TEN N ES S E E 37401 400 Chestnut Street Tcwer II gp - 6'l b 5~l ) I20 d I January 15, 1081 Mr. Ju es P. O'Reilly, Diretor Office of Inspection and Enfercement U.S. Nuclear Regulatory Co'oission Region II - Suite 3100 101 Marietta Street Atlanta, Georgia 30303
Dear Mr. O'Reilly:
HARTSVILLE NUCLEAR PLA!;T UNIT A1 - REPORTABLE DEFICIENCY - HEATEPS OMITTED FROM !OTOR OPERATOR - SUPPLE!' ENTAL I?IFOR!*ATION (NCR HNP-A-097)
Initial notification of the subject deficiency was made to MRC-CI2 Perion II Inspector R. W. Wright en June 18, 1480. The final and the first supplenental reports were submitted on July 18 and Dececher 2?,1^90, respectivaly. Bis letter constitutes "!A's second su plemental response o't the subject deficiency.
GE has informed TVA that it anticipates shipping the replace"!ents for the deficient motors by November 1, 1981, in order to complete the corrective actions for this nonconformance.
If you have any questions, please call Jim Domer at FTS 357-2014 Very truly yours, TE!!NESSCE VALLEY AUTHODITY L. M. Mills, Manager Nuclear Regulatien and Safety cc:
Mr. Victor Stello, Director Office of Inspection and Snforcement U.S. Nuclear Pegulatory Commission Washington, DC 20555
<-~