Responds to NRC Re Violations Noted in IE Insp Repts 50-424/82-11 & 50-425/82-11.Corrective Actions: Contractor Directed to Be More Selective in Choosing Pipe Spool Storage Areas & Assign Addl Personnel to Monitor Area
ML20062K016
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 07/28/1982
From: Foster D
GEORGIA POWER CO.
To: Long F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML20062J966 List:
References
GN-183, NUDOCS 8208160524
Download: ML20062K016 (2)


Text

, ,

e Georgia Power Company *,J; -

Post Offee Box 4545 .

Atlanta, Georgia ?0302 Telephone 404 522-6060 g Vogtle Proj.ect 2 ~S 7~ ^2 16 Southern Company Servces, Inc.

Post Offee Box 2625 Bamingham, Alabama 35202 Telephone 205 870-6011 July 28, 1982 United States Nuclear Regulatory Commission Office of Inspection and Enforcement Region II - Suite 3100 101 Marietta Strect File: X7BG10 Atlanta, Georgia 30303 Log: GN-183

Reference:

ID: II:

50-424/82-11 50-425/82-11 Attention: F. J. Long Gentlemen:

The Georgia Power Company wishes to submit the following infonnation concerning the violations discussed in your inspection report 50-424/82-11 and 50-425/82-11.

We concur with the finding identified concerning failure to control the storage and preservation of material. The reason for the violation was failure to properly follow procedures in storing the piping assemblies.

The affected pipe spools have been stored correctly. Contractors have been directed to use more care in the storage of pipe spools. The contractor will be more selective in requisitioning pipe spools in order to reduce the amount of storage required. The contractor will be more selective in choosing spool storage areas and will assign additional personnel to monitor the storage.

Full compliance was achieved on May 11, 1982.

We concur with the finding identified concerning failure to have survey procedures. The reason for the violation was the sarvey procedures that existed were deleted because experience indicated that normal survey

, practice was adequate to ensure quality work.

A new field procedure to control survey activities was approved on July 25,1982. Our ongoing training program on procedure requirements and audit program on procedure implementation should prevent reoccurrence of further violations.

Full compliance should be achieved by August 13, 1982.

8208160524 820804 PDR ADOCK 05000424 O PDR

f. J. Long

. 50-424/82-11; 50-425/82-11 l July 28, 1982  :

Page 2 i

This response contains no proprietary infonnation and may be placed ;

in the fiRC Public Document Room upon receipt.  ;

Yours truly,  !

,o /

. . Foster Project General Manager i D0F/CWH/tlp xc: U. S. Nuclear Regulatory Commission Attn: Victor J. Stello, Jr. , Director Office of Inspection and Enforcement llashington, D. C. 20555 R. J. Kelly R. E. conway G. F. Head J. T. Beckham, Jr.

J. H. Boykin D. E. Dutton R. H. Pinson l D. L. McCrary

' R. A. Thomas J. A. Bailey

0. Batum H. H. Gregory, III E. D. Groover L. T. Gucwa M. Malcom C. R. Miles, Jr.

M. Manry P. D. Rice R. W. Staffa J. L. Vota W. F. Sanders - Resident Inspector l

l I

l