Forwards Draft Revision 10 to Inservice Testing of Plant Valves, Per NRC Inservice Test Program Review & 820618 Conference Call.Comments Requested Complete Final Draft
ML20062G660
Person / Time
Site: Palisades Entergy icon.png
Issue date: 08/06/1982
From: Johnson B
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To: Crutchfield D
Office of Nuclear Reactor Regulation
Shared Package
ML18047A512 List:
References
NUDOCS 8208130116
Download: ML20062G660 (1)


Text

1

.s s.

4 CORSum8tS Power Company General offices: 1945 West Parnali Road, Jackson, MI 49201 * (517) 788 0550 August 6, 1982 Dennis M Crutchfield, Chief Operating Reactor Branch No 5 Nuclear Beactor Regulation US Nuclear Regulatory Commission Washington, DC 20555 DOCKET 50-255 - LICENSE DPR PALISADES PLANT - UPDATE OF INSERVICE VALVE TEST PROGER4 Consumers Power Company submitted an updated copy of our Inservice Valve Test Program (with attached relief requests) for the Palisades Plant on October 28, 1981. This submittal was made in order to comply with the requirements of the ASME Boiler and Pressure Vessel Code, Section XI: 1977 edition with Addenda through summer 1979 Subsequently, the NRC raised several questions concerning this report in its Palisades Inservice Test Program Review (PITPR) which were discussed in a conference call betvcen Consumers Power Company and the NRC staff on June 18, 1982.

Attached to this letter is a revised draft of the procedures for Inservice Testing of Plant Valves, EM-09-02, which is the result of the NRC's PITPR and the June 18, 1982 conference call.

Consumers Power Company requests that the NRC staff review this document and provide any questions or comments raised in order for us to complete a final draft of these procedures.

WW M'

Brian D Johnson Staff Licensing Engineer CC Administrator, Region III, USNRC NRC Resident Inspector - Palisades Atta':n=ent 04'{

F208130116 820806 PDR ADOCK 05000255 p

PDR