ML20062E607
| ML20062E607 | |
| Person / Time | |
|---|---|
| Site: | Waterford |
| Issue date: | 07/30/1982 |
| From: | Mclendon G LOUISIANA POWER & LIGHT CO. |
| To: | Jay Collins NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| References | |
| 10CFR--50.55E, 10CFR-050.55E, 10CFR-50.55E, W3K-82-0467, W3K-82-467, NUDOCS 8208100169 | |
| Download: ML20062E607 (1) | |
Text
9 LoulSIANA f 242 OuAnoNot SrnEe1 POWE R & LiG H T/ P O BOX 6006 + NEW ORLEANS. LOUISIANA 70174 * (504) 366-2345
'$EONbsYO3 u
July 30, 1982 G D. McLENDON Senior Vice President W3K 0467 Q-3-A35.07.47 Mr. John T. Collins, Regional Administrator, Region IV f.. i, J Ny n
- -- m l dl)h dI:[
I U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 q
r Arlington, Texas 76012 gg gl 2 y
l 1
Subject:
Waterford SES Unit No. 3 L
i--
Docket No. 50-382 Significant Construction Deficiency No. 47 "G.E. AKR 30/50 Circuit Breakers Closing Spring Screw" Second Interim Report
Reference:
LP&L Letter W3K-82-0392 dated July 6, 1982
Dear Mr. Collins:
Corrective action on Significant Construction Deficiency No. 47 was to be completed by July 30, 1982, at which time the final report was to be submitted. We are unable to meet the previously stated schedule.
As only a small amount of work is necessary to complete the required corrective action, it is anticipated that the final report on Significant Construction Deficiency No. 47 will be submitted by August 13, 1982.
l If you have any questions, please advise.
1 Very truly yours,
/
M l
GDMcL/LLB/grf cc:
- 1) Director Office of Inspection & Enforcement l
U. S. Nuclear Regulatory Commission Washington, D. C. 20555
- 2) Director Office of Management y
Information and Program Control 2
U. S. Nuclear Regulatory Commission Washington, D. C. 20555 8208100169 820730 PDR ADOCK 05000392
\\
S PDR