Notification of 820824-26 Meetings W/Util at Site to Observe Const & Obtain Info Re Completion of Const & Preoperational Tests for NRC Caseload Forecast Panel
ML20062C167
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 07/27/1982
From: Kintner L
Office of Nuclear Reactor Regulation
To: Youngblood B
Office of Nuclear Reactor Regulation
References
NUDOCS 8208050182
Download: ML20062C167 (6)


Text

'

o ..

JUL 2 71982 Docket No.: 50-341 MEf0RANDUM FOR: B. J. Youngblood, Chief, Licensing Branch No.1 DL FROM: L. L. Kintner, Project Manager, Licensing Branch No.1, DL

SUBJECT:

FORTHCOMING MEETING WITH DETROIT EDISON COMPANY REGARDING FERMI 2 OPERATING LICENSE REVIEW DATE AND TIME: August 24, 25 & 26, 1992 9:00 AM LOCATION: Fermi 2 Plant Monroe County, Michigan PURPOSE: Observe construction and obtain information regarding completion of construction and preoperational tests for use by the NRC Caseload Forecast Panel (Agenda attached)

PARTICIPANTS: NRC Staff W. Lovelace, B. Little, B. J. Youngblood, L. Kintner Detroit Edison Company W. Fahrner, S. H. Noetzel, R. A. Vance, L. Schuerman orisiL(,gigned y,intner W Lecter L. L. Kintner, Project Manager Licensing Branch No. 1 Division of Licensing

Enclosure:

Agenda cc w/ encl . : See next page 1

8208030182 820727 PDR ADOCK 05000341 A PDR fl At M v omce> D(,:(B,(,1,

, [ DL b LLKintner/lg BJ gbl od suaucue >

oare p 26782"""'

W T'""'

~ ~ ~ ~

NRC FORM 318 (10-80) NRCM 024o OFFICIAL RECORD COPY use.mim-u m

Mr. Harry Tauber Vice. President Engineering & Construction Detroit Edison Company 2000 Second Avenue Detroit, Michigan 48226 cc: Mr. Harry H. Voigt, Esq.

LeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Avenue, N. W.

Washington, D. C. 20036 Peter A. Marquardt, Esq.

Co-Counsel The Detroit Edison Company 2000 Second Avenue Detroit, Michigan 48226 Mr. William J. Fahrner Project Manager - Fermi 2 The Detroit Edison Company 2000 Second Avenue Detroit, Michigan 48226 Mr. Larry E. Schuerman Detroit Edison Company 3331 West Big Beaver Road s' Troy, Michigan 48084 _

David E. Howell, Esq.

3239 Woodward Avenue Berkley, Michigan 48072 Mr. Bruce Little U. S. Nuclear Regulatory Commission Resident Inspector's Office 6450 W. Dixie Highway Newport, Michigan 48166 Dr. Wayne Jens Detroit Edison Company 2000 Second Avenue Detroit, Michigan 48226 Mr. James 13. Keppler Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 l

l

.i

m

- v.--

  • s t -1 .

FERMI 2 CASELOAD FORECAST PANEL SITE VISIT MEETING AGENDA

1. Overview of project construction schedule including progress and major milestones completed, current problems and any anticipated problem areas that may impact the current projected fuel load date.
2. Detailed review and current status of design and engineering effort (by major discipline) including any potential problems that may arise from necessary rework.
3. Detailed review and current status of procurement activities including valves, pipe, instruments, cable, major components, etc.
4. Actual and proposed craft work force (by najor craft), craft availability, productivity, potential labor negotiations and problems.
5. Detailed review and current status of all large and small bore ~

pipe hangers, restraints, snubbers, etc. , including design, -

rework, procurement, fabrication, delivery and installation.

6. Detailed review of project schedule identifying critical path '

items, near critical items, amount of float for various activities, the current critical path to fuel loading, methods of implementation of corrective action for any activities with negative float, and provisions for contingencies. The estimated project percent complete ,

as of July 31, 1982.

7. Detailed review and current status of bulk quantities including current estimated quantities, quantities installed to date, quantities scheduled to date, current percent complete for w each, actual versus forecast installation rates, in cubic yards /mo., 's linear feet /mo. , or number /mo. , and basis for figures.

(a) Concrete (CY)

(b) Process Pipe (LF)

- Large Bore Pipe (21/2" and larger)

- Small Bore Pipe (2" and smaller) ,

(c) Yard Pipe (LF)

(d) Large Bore Pipe Hangers, Restraints, Snubbers (ea) . 3

\

\

  • 4

(e) Small Bore Pipe Hangers, Restraints (ea)

(f) Cable Tray (LF)

(g) Total Conduit (LF)

(h) Total Exposed Metal Conduit (LF)

(1) Cable (LF)

- Power

- Control J - Security

- Instrumentation

- Plant Lighting (j) Terminations (ea)

- Power

- Control

- Security

- Instrumentation

- Plant Lighting (k) Electrical Circuits (ea)

- Power

- Control

- Security (1) Instrumentation (ea)

8. Detailed review and current status of preparation of preop and acceptance test procedures, integration of preop and acceptance test activities with construction schedule, system s turnover schedule, preop and acceptance tests schedule, current and proposed preop and acceptance tests program manpower.

~

(a) Total number of procedures required for fuel load.

(b Number of draft procedures not started.

(c Number of draft procedures being written.

(d Number of procedures approved.

(e) Number of procedures in review.

-(f) Total number of preop and acceptance tests required for fuel load.

~ (g) Number of preop and acceptance tests completed.

(h) Number of preop and acceptance tests currently in 7

. .. . 1 progress.

h (i) Number of systems turned over to start-up.

(j) Number of preop and acceptance tests scheduled

~

for starting as of July 31, 1982.

'~:

  • i
9. Detailed discussion of potential schedular influence due to changes attributed to NUREG-0737 and other recent licensing requirements.
10. Discussion of schedular impact, if any, regarding potential deficiencies reported in accordance with 10 CFR 50.55(e).

11, Overview of current construction and startup management organization showing interfaces between the two.

12. Site tour and observation of construction activities.

r ,,

44 w MEETING NOTICE IDocismeiU6ktN12(502341)W  :

NRC PDR JUl. 2 7 N .

L PDR TERA NSIC LB#1 Rdg.

MRushbrook Project Manager L. Kintner E. Case D. Eisenhut/R. Purple T. Ilovak.

J. Youngblood A. Schwencer F. Miraglia E. Adensam SSPB Branch Chief G. Lainas W. Russell D. Crutchfield T. Ippolito J. P. Knight W. Johnston D. Muller T. Speis ,- ._

R. Houston -

L. Rubenstein F. Schroeder M. Ernst J. Kramer Attorney, OELD OIE Regional Administrator, Region III ACRS (16) f OSD(7) /-

\

PARTICIPANTS (NRC)1 W. Lovelace B. Little-RI -

J. Youngblood L. Kintner i

. J

.