ML20062A487

From kanterella
Jump to navigation Jump to search
Advises of Completion of Mod to Reactor Core Isolation Cooling Sys Automatic Restart Per NUREG-0737,Action Item II.K.3.13.Requests Items Be Closed
ML20062A487
Person / Time
Site: Shoreham File:Long Island Lighting Company icon.png
Issue date: 07/29/1982
From: James Smith
LONG ISLAND LIGHTING CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.K.3.13, TASK-TM NUDOCS 8208040009
Download: ML20062A487 (1)


Text

f LONG ISLAND LIGHTING COM PANY g'gg A.a V. ## sar/ w w SHOREHAM NUCLEAR POWER STATION P.O. BOX 618, NORTH COUNTRY ROAD e WADING RIVER, N.Y.11792 July 29, 1982 SNRC-744 Mr. Harold R.

Denton, Director Office of Nuclear Reactor Regulation U.S.

Nuclear Regulatory Commission Washington, D.C.

20555 NUREG 0737, Item II.K.3.13 RCIC Automatic Restart Shoreham Nuclear Power Station - Unit 1 Docket No. 50-322

Reference:

Letter SNRC-586 dated 6/11/81

Dear Mr. Denton:

In accordance with the NRC's position contained in NUREG 0737, Item II.K.3.13, the Long Island Lighting Company agreed to provide automatic restart capability for the Reactor Core Isolation Cooling System following trip at reactor high water level.

Restart would be initiated upon reactor water level again reaching the low level initiation point.

To this end, LILCO, via the reference letter, provided con-ceptual design details and a commitment to install this feature, to the extent possible, prior to fuel load.

The NRC found this acceptable as documented in Supplement No. 1 to the Safety Evaluation Report, and this item was classified " Approved pending confirmation."

The purpose of this letter is to advise you that installation and preoperational testing of this modification has been completed.

LILCO requests that confirmatory actions be initiated as deemed appropriate by the staff so that this item, II.K.3.13, can be completely closed on the Shoreham docket.

Should you have any questions, please contact this office.

Very truly yours, Sk l

(

L.

Smith Manager, Special Projects Shoreham Nuclear Power Station RWG:mp cc:

J.

Higgins 8208040009 820729 All parties PDR ADOCK 05000322 A

PDR k