ML20059K953

From kanterella
Jump to navigation Jump to search
Provides Listed Info Outlining Tests Being or That Have Been Conducted on Dgs.Outline Also Contains Approx Times When Future Tests Will Be Performed
ML20059K953
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 01/26/1994
From: Link B
WISCONSIN ELECTRIC POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
CON-NRC-94-007, CON-NRC-94-7 VPNPD-94-013, VPNPD-94-13, NUDOCS 9402020386
Download: ML20059K953 (3)


Text

j_ 3

.I

^

Wisconsin Electnc

, POWER COMPANY 231 w uomn co ecu ra46.Mw23%.w 532002046 (4 41221-2345 VPNPD-94-013 NRC-94-007' January 26, 1994 Document Control Desk U.S. NUCLEAR REGULATOR'- UMMISSION Mail Station P1-137 Washington, DC 20555 Gentlemen:

DOCKETS 50-266 AND 50-301 TESTING OF THE NEW EMERGENCY DIESEL GENERATORS POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 In response to the NRC staff reviewers' questions pertaining to testing of the diesel generators for the Point' Beach Nuclear Plant Diesel Generator Addition Project, we are providing the following information which outlines the tests that are being, or have been, conducted on the diesel generators. The outline also-contains approximate times when future tests will be performed. -

Factory Accentance Testina Factory acceptance testing was successfull'y completed during December of 1993 on both~of the emergency diesel generators:

.1. Performance tests per paragraphs 6.2.1.2a through 6.2.1.2d of IEEE Std 387-1984

2. Single-Load Rejection-Test equal to our largest single load
3. Full-Load Rejection Test
4. Transient Tests 0 - 25% Load Step  :
f. 0 - 50%- Load Step  ;

O - 75% Load Step j 0.- 100% Load Step l 3.002$ , t ,

9402020386 940126 i PDR .ADOCK 05000266 P- PDR i: AsubsitingofHhaminEnew anxvanw L.

.. :s_

I i

'l Document Control Desk j

January 26,- 1994 I Page 2 l

The following testing was completed on one of the emergency diesel generators:

1. Start and Load Acceptance Tests consisting of 30 consecutive successful start and load tests
2. Load Acceptance Test (Load Profile Test)
3. Margin Test per the IEEE Standard 387-1984 ,
4. 24-Hour Endurance Test 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> at 2987 kW and 22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> at ,

2951 kW, rated load is 2850 kW .}

Site Accentance Testina Site acceptance testing will be performed in two phases. The:first -

phase will consist of the tests shown below and will be' performed prior to permanent tie-in to the plant. The tests will be ,

performed by using a temporary connection to the electrical i distribution system.

1. Start Tests (25 starts per unit) ,

i

2. Load-Run Test ,

l'

3. Fast-Start Test
4. Hot Restart Test These tests are scheduled to be conducted during August.and -

September of 1994. 1 The second phase of testing will be conducted during the tie-in phase of'each diesel. These tie-ins will be performed ~during the  :

refueling outages for.each unit.  !

i

1. Synchronizing Test
2. Protective Trip Bypass Test )
3. Test Mode Change-over Test

.: l

4. Redundant. Unit Test 'l S. Loss-of-Offsite-Power (LOOP) Test i
6. Safety-Injection-Actuation-Signal (SIAS) Test  !

1

[. '. . 3 -

l P ..l Document Control Desk January 26, 1994 Page 3 y

)

l

7. Combined SIAS and LOOP Test. This test will be only run as an "

SIAS coincident with a LOOP. A delayed SIAS or LOOP scenario.

will not be conducted. This is consistent the current testing .

process for existing emergency diesel generators.  !

'The projected schedule for these tests is as follows:

October 1994 EDG G-04 to Unit 2, B Train (2A-06)

April 1995 EDG G-03 to Unit 1, B Train (1A-06) and EDG G-04 to Unit 1, B Train (1A-06)

October 1995 EDG G-03 to Unit 2, B Train (2A-06) and EDG G-02 to Unit 2, A Train (2A-05)

April 1996 EDG G-02 to Unit 1, A Train (1A-05)

A Technical Specification amendment request to allow the use of the new emergency diesel generators is being prepared for submittal.

We expect to submit the request during the second quarter of 1994.

Approval of_the. Technical Specification amendment request will be necessary by September 1994 to allow the tie-ins to begin in October 1994 as scheduled. Therefore, observation of the tie-in testing by the NRC Technical Staff will not be possible prior to issuance of the Technical Specification amendment.

Please contact us if there are any questions.

Sincerely, g , "y]

Bo L[n Vice President Nuclear Power CAC/jg cc: NRC Regional Administrator, Region III NRC Resident Inspector Public Service Commission of Wisconsin