Text
a
pm Rtcg
UNITED STATES
[
[\\
NUCLEAR REGULATORY COMMISSION
f ( N2 I
REGION IV
IIh
[
611 RYAN PLAZA DRIVE, SUITE 400
AR U NGTON. T E X AS 760118064
g*ay j
.....
NOV - 91993
Dockets:
50-313
50-368
Licenses:
NPF-6
.
Entergy Operations, Inc.
ATTN:
J. W. Yelverton, Vice President
Operations, Arkansas Nuclear One
Route 3, Box 137G
Russellville, Arkansas 72801
SUBJECT: NRC INSPECTION REPORT 50-313/93-08; 50-368/93-08 (NOTICE OF
DEVIATION)
This refers to the inspection conducted by Ms. L. J. Smith, and the inspectors
identified in the enclosed report, of this office on August 22 through
October 2, 1993. The inspection included a review of activities authorized
At the conclusion of
-
for your Arkansas Nuclear One, Units 1 and 2, facility.
the inspection, the findings were discussed with those members of your staff
identified in the enclosed report.
.
Within
Areas examined during the inspection are identified in the report.
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observation of
The purpose of the inspection was to determine
activities in progress.
whether activities authorized by the license were conducted safely and in
accordance with NRC requirements.
Based on the results of this inspection, certain of your activities appeared
to deviate from your commitments in the Safety Analysis Report, as specified
in the enclosed Notice of Deviation (Notice). We are concerned about the
deviations because failure to administratively control nitrogen isolation
valves in accordance with Table 5 of the Safety Analysis Report posed a
potential for compromising containment integrity. Additionally, the potential
to degrade safety-related piping in Level D storage areas existed.
It is our understanding that, during an exit meeting conducted on
October 7, 1993, Mr. J. Vandergrift, Unit 1 Plant Manager, committed to
corrective actions delineated in Section 3.2 and Section 3.4 for unlocked
closed containment isolation valves _ and Level 0 storage of items,
respectively.
If your understanding of this comitment differs from ours,
please contact me immediately.
l
9311160084 931109
~ ,
ADOCK 05000313-
'
G
FDR
I
-
.
_-.
-
. . .
.
.
.
!
.
.
, , -
Entergy Operations, Inc.
-2-
NFJ/-9 m
1
i
!
Although 10 CFR 2.201 requires you to submit to this office, within 20 days of
j
your receipt of this Notice, a written statement of explanation, we note that
'
the corrective actions being taken adequately address the concerns identified
j
within the Notice of Deviation. Therefore, no response with respect to the
Notice is required.
j
!
'
In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of
-
this letter and its enclosures will be placed in the NRC Public Document Room.
Should you have any questions concerning this inspection, we will be pleased
to discuss them with you.
j
!
Sincerely,
.
A. Bill Beach,
ire to
i
l
Division of Rea to Praje s
'
Enclosures:
1.
Appendix "i - Notice of Deviation
l
2.
Appendix 8 - NRC Inspection Report
i
50-313/93-08; 50-368/93-08
i
!
cc w/ enclosures:
,
Entergy Operations, Inc.
i
ATTN: Harry W. Keiser, Executive
i
Vice President & Chief Operating Officer
l'
P.O. Box 31995
Jackson, Mississippi 39286-1995
i
Entergy Operations, Inc.
ATTN: John R. McGaha, Vice President
i
Operations Support
i
!
P.O. Box 31995
Jackson, Mississippi
39286
)
Wise, Carter, Child & Caraway
.l
ATTN: Robert B. McGehee, Esq.
j
P.O. Box 651
-
Jackson, Mississippi
39205
--
!
.
'
-!
?
,
!
i
l
t
.
.
.
.~ -
.
N-'
A
'
Entergy Operations, Inc.
-3-
4N
,
Entergy Operations, Inc.
.
ATTN:
Rick King
Acting Director, Licensing
,
RouteL3, Box 137G
,
Russellville, Arkansas 72801
>
,
Entergy Operations, Inc.
-
ATTN: Michael B. Sellman, General
Manager, Plant Operations
Route 3, Box 137G
Russellville, Arkansas 72801
<
,
Honorable C. Doug Luningham
!
'
County Judge of Pope County
!
Pope County Courthouse
Russellville, Arkansas 72801
,
,
Winston & Strawn
l
ATTN: Nicholas S.- Reynolds, Esq.
1400 L Street, N.W.
Washington, D.C.
20005-3502
-
Arkanss3 Department of Health
j
ATTN: Ms. Greta Dicus, Director
Division of Radiation Control and
i
Emergency Management
!
4815 West Markham Street
i
Little Rock, Arkansas 72201-3867
B&W Nuclear Technologies
ATTN: Robert B. Borsum
'
Licensing Representative
1700 Rockville Pike, Suite 525
.:
Rockville, Maryland 20852
!
Admiral Kinnaird R. McKee, USN (Ret)
!'
214 South Morris Street
0xford,. Maryland 21654
ABB Combustion Engineering
-
Nuclear Power
t
ATTN: Charles B. Brinkman
!
Hanager, Washington
Nuclear Operations
j
12300 Twinbrook Parkway, Suite 330
.!
Rockville, Maryland 20852
~
!
i
..
1
e
o
1
!
'
.
_
. ~ ~ .
-
,.
, .
..
.
.
. _ .
__
_
.
'
-[
-
-;
. .
10/ - 9.1993
'Entergy Operations, Inc.
- 4..
- i
!
I
bec to DMB_(IE01)
]
bec distrib. by RIV:
.
i
J. L. Milhoan
Resident Inspector-
.
.i
-
Section Chief (DRP/D)
Lisa.Shea, RM/ALF, MS: MNBB 4503
[
MIS System
DRSS-FIPS
RIV File
Section Chief (DRP\\TSS)
[
"
Project Engineer (DRP/D)
A. B. Beach, D:DRP '
Richard Rozano, MS:0WFN 7H5
.
-l
.
t
!
i
!
!
!
.l
-
,
- i
.-j
!
_
.
I-;.;
-
^'
.
!
RIV:EA:DRP/D,3
RI:DRP/DWh
SRI:DRP/d
PE:DRP/Ddh-
C:DRP/D.d() -
j
KDWeaver:vd. SJCampbellh-
LJSmithh
SMcCoryjIk
TFStetka
'
!
,
11/p3/93
-
11/B /93-
11/8,/93
11/8 /93
II/g /93
D:DRP (N
ABBeach.b,(
J
11/f /93 (
l
a
.-
.
=?
,
.,
,
_
.w
-!
U ~9 N
-Entergy Operations,.Inc.
-4-
-j
t
!
!
!
Scc 3d;DMBillEdi)
(
,
bec.distrib. by RIV:
J. L. Milhoan
Resident Inspector
'
Section Chief (DRP/D)
Lisa Shea, RM/ALF, MS: MNBB 4503
MIS System
DRSS-FIPS-
.
i
-
RIV File
Section Chief (DRP\\TSS)
-
Project Engineer (DRP/D)
A. B. Beach, D:DRP
i
'
Richard Rozano, MS:0WFN 7HS
i
!
.i
'I
.
.1
!
i
I
t
t
,.!
!
i
<: i i
. .
!
l,.
RIV:EA:DRP/Da
RI:DRP/Dtd[
SRI:DRP/9d
PE:DRP/BM
C:DRP/D J -
TFSt'etka
.f
KDWeaver:yk
SJCampbelik
LJSmith[
SMcCoryh.i
4
.
II/p3/93
11/8 /93
11/S./93
11/8/93 ~
'll/g /93
!
.
D':DRP [M
f
ABBeach \\,h .
1
-!
'
11/i/93 (
,,
!
!
Lj
.1
- ^
.
.
-,