Advises of Plan to Conduct Insp of Implementation of Station Blackout Rule on 940103,per 931102 Discussion.Team Would Like to Conduct Short Entrance Meeting W/Involved Members on 940103.Encl List of Matls Required for Insp
ML20059H525
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 11/05/1993
From: Collins S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Tira Patterson
OMAHA PUBLIC POWER DISTRICT
References
NUDOCS 9311100111
Download: ML20059H525 (5)


Text

.

pH # f C UMITED STATES y-

?g NUCLEAR REGULAVORY COMMISSION

[.i L '

j REGION IV

-f

~8 611 RY AN PLAZA DRIVE SUITE 400 c.

54 s., _f AR LINGT ON, T E X AS 76011 8064

[

NOV - 51993 l

i Docket: 50-285 i

License: DPR-40 l

l l

Omaha Public Power District ATTN:

T. L. Patterson, Division Manager Nuclear Operations

{

Fort Calhoun Station FC-2-4 Adm.

P.O. Box 399, Hwy. 75 - North of Fort Calhoun Fort Calhoun, Nebraska 68023-0399 I

l

SUBJECT:

STATION BLACK 0UT RULE IMPLEMENTATION NRC INSPECTION REPORT N0. 50-285/94-01 We are planning to conduct an inspection of the implementation of the Station Blackout Rule,10 CFR 50.36, at your Fort Calhoun Station during the week of January 3, 1994.

This inspection schedule was discussed with Mr. Cook of your

.i staff on November 2, 1993.

i i

The inspection will be conducted-in accordance'with Temporary Instruction

)

2515/120, " Inspection of Implementation of Station Blackout Rule Multi-Plant-r Action Item A-22."

The Team Leader and principal contact for this inspection effort is Mr. Philip Wagner. The inspection team will-consist of the Team i

Leader, two Region IV inspectors, and two NRR engineers.

In order to implement an efficient inspection, the team would like to conduct a short entrance meeting with those involved members 'of your staff at 11 a.m.

on January 3, 1994. The team would appreciate a short (one hour) presentation on the history and status of all changes made to meet the requirements of the Station Blackout Rule at the conclusion of the entrance meeting.

The Team Leader will ensure that the necessary access authorization information is provided prior to the inspection. 'For those team members who do not have current access approval, we request that the necessary training be l

conducted after the entrance meeting on January 3', 1994.

I Attached to this letter is a list of materials that the team will require for i

the inspection. We request that the material be'available for the' team review and reference on January 3.1994.

9311100111 931105 PDR ADOCK 05000285 G

PDR L

i Omaha Public Power District !

Should you have any questions on the inspection or the requested material, please contact Mr. Wagner at (817) 860-8127.

j Sincerely, i'

f GhwL fi.

. Collins, Director, Division of Reactor Safety

Attachment:

As Stated cc w/ attachment:

}

LeBoeuf, Lamb, Leiby & MacRae ATTN: Mr. Michael F. McBride 1875 Connecticut Avenue, NW

[

Washington, D.C.

20009-5728 j

Washington County Board f

of Supervisors ATTN: Jack Jensen, Chairman i

Blair, Nebraska 68008 l

Combustion Engineering, Inc.

ATTN: Charles B. Brinkman, Manager 1

Washington Nuclear Operations 12300 Twinbrook Parkway, Suite 330 t

Rockville, Maryland 20852 l

Nebraska Department of Health ATTN: Harold Borchert, Director Division of Radiological Health 301 Centennial Mall, South 1'

P.O. Box 95007 Lincoln, Nebraska 68509-5007 i

Fort Calhoun Station ATTN: James W. Chase, Manager P.O. Box 399 Fort Calhoun, Nebraska 68023 j

i I

i Omaha Public Power District 1 rbec to DMB-(IE01)--

bcc distrib. by RIV:

J. L. Milhoan Resident Inspector DRSS-FIPS MIS System RIV File Section Chief (DRP/TSS)

Lisa Shea, RM/ALF, MS: MNBB 4503 Senior Resident Inspector - Cooper G. Embro, NRR T. Westerman P. Wagner RIV:TLMO)

C:ES T C:DRP/DY /AM I AD:DRP/

D:C

[Cfh TPfshnn

[JCb1bns, /

PWagner/lb TFWesterman TFStetka

1) /J /93

}! /%/93

\\\\ / 3 /93 Y93

[ / /93 b 090041

Omaha Public Power District,

bec to DMB (IE01) bcc distrib. by RIV:

J. L. Milhoan Resident Inspector DRSS-FIPS MIS System RIV File Section Chief (DRP/TSS)

Lisa Shea, RM/ALF, MS: MNBB 4503 Senior Resident Inspector - Cooper G. Embro, NRR T. Westerman P. Wagner i

RIV:TL9M C:ES T C:DRP/Dh M AD:DRP/

D:C PWagner/lb TFWesterman TFStetka

[CIhNa[

TPknn

[JCbibns, /

11 /. 3 / 9 3

}l / % /93

\\\\ /S /93 Y 93

// /93 M i

-+

A ATTACHMENT LIST OF MATERIALS 1.

Copies of the submittals that describe how compliance with the Station Blackout Rule will be achieved.

2.

Copies of Station Procedures that will be implemented in the event of a blackout condition.

3.

Copies of the battery capacity calculations that verify acceptable coping time.

4.

Copies of calculations that verify that acceptable stored cooling water volume is available.

5.

Copies of calculations to verify that acceptable levels of equipment cooling will be maintained; particularly the control room and control components.

6.

Copies of calculations that verify that the backup air supplies are adequate for the coping duration.

7.

Copies of the surveillance procedures to verify the adequacy of the backup air supplies.

8.

Data that presents the reliability of the offsite and onsite power supplies.

9.

Copies of facility structures elevation drawings for team member use in i

locating equipment.

i l

.