Forwards Amend 169 to License DPR-61 & Safety Evaluation. Amend Changes TS by Incorporating New Section 3/4.8.3.1.2, Onsite Power Distributions
ML20059G619
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 11/01/1993
From: Wang A
Office of Nuclear Reactor Regulation
To: Opeka J
CONNECTICUT YANKEE ATOMIC POWER CO., NORTHEAST NUCLEAR ENERGY CO.
Shared Package
ML20059G624 List:
References
TAC-M87247, NUDOCS 9311080271
Download: ML20059G619 (3)


Text

_ _ _

~

November 1, 1993 Docket No. 50-213 Distribution:

Docket File CGrimes NRC & Local PDRs ACRS (10)-

PD I-4 Plant OPA Mr. John F. Opeka SVarga OC/LFDCB Executive Vice President, Nuclear JCalvo LTDoerflein, RG I Connecticut Yankee Atomic Power Company SNorris WBeckner i

Northeast Nuclear Energy Company AWang CBerlinger Post Office Box 270 OGC j

Hartford, Connecticut 06141-0270 DHagan GHill (2)

Dear Mr. Opeka:

SUBJECT:

ISSUANCE OF AMENDMENT (TAC NO. M87247) l The Commission has issued the enclosed Amendment No.169 to Facility Operating License No. DPR-61 for the Haddam Neck Plant, in response to your application dated August 18, 1993.

The amendment changes the Haddam Neck Technical Specifications (TS) by incorporating a new TS Section 3/4.8.3.1.2, "0NSITE POWER DISTRIBUTION." The new TS will incorporate an additional limiting condition for operation (LCO) into the TS which will require that the 480 VAC motor control center 5 and its automatic bus transfer scheme be operable during Modes 1, 2, 3, and 4.

In addition the LCO currently numbered 3.8.3.1 and the surveillance requirement currently numbered 4.8.3.1 will be renumbered 3.8.3.1.1 and 4.8.3.1.1, respectively, to support the incorporation of the additional LCO.

A copy of the related Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's biweekly Federal Reaister notice.

l Sincerely, j

Original signed by:

I Alan B. Wang, Project Manager Project Directorate I-4 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation

Enclosures:

ht h

h/ /

1.

Amendment No.169 to DPR-61 h

2.

Safety Evaluation MnG

~ >p# fA gq' cc w/ enclosures:

8 r>f See next page p)

OFFICE LA:PDI-4

.,PM:PDI-4 BC:SPSB BC: EEL M DIhDI-4 OGQg[

"W S

AWang5tfp YUd$Yr CBerlinger Jhtdk 9/70/93

$/h/93

/0/5793 S/30/93 10/

/93 I

/ // V/93 gi DME

/

i 0FFICIAL RECORD COPY t

Document Name: G:\\ WANG \\ABT.amd h)M b b 9311080271 931101 c

PDR ADOCK 05000213 P

PDR-

l ff t

UNITED STATES j

.j NUCLEAR REGULATORY COMMISSION iW

  • I E

WASHINGTON. D.C. 20566-0001

\\...../

November 1, 1993 Docket No. 50-213 Mr. John F. Opeka Executive Vice President, Nuclear Connecticut Yankee Atomic Power Company-Northeast Nuclear Energy Company Post Office Box 270 Hartford, Connecticut 06141-0270

Dear Mr. Opeka:

SUBJECT:

ISSUANCE OF AMENDMENT (TAC NO. M87247)

The Commission has issued the enclosed Amendment No.169 to Facility Operating License No. DPR-61 for the Haddam Neck Plant, in response to your application dated August 18, 1993.

The amendment changes the Haddam Neck Technical Specifications (TS) by incorporating a new TS Section 3/4.8.3.1.2, "0NSITE POWER DISTRIBUTION." The new TS will incorporate an additional limiting condition for operation (LCO) into the TS which will require that the 480 VAC motor control center 5 and its automatic bus transfer scheme be operable during Modes 1, 2, 3, and 4.

In addition the LC0 currently numbered 3.8.3.1 and the surveillance requirement currently numbered 4.8.3.1 will be renumbered 3.8.3.1.1 and 4.8.3.1.1, respectively, to support the incorporation of the additional LCO.

A copy of the related Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commission's biweekly Federal Reaister notice.

Sincerely,

{k:% NG.

Alan B. Wang, Project Manager Project Directorate I-4 Division of. Reactor Projects - I/II Office of Nuclear Reactor Regulation

Enclosures:

1.

Amendment No.169 to DPR-61 i

2.

Safety Evaluation cc w/ enclosures:

See next page

-v-

-.e

,r

-~

Mr. John F. Opeka Haddam Neck Plant i

Northeast Nuclear Energy Company l

j cc:

a Gerald Garfield, Esquire R. M. Kacich, Director Day, Berry and Howard Nuclear Licensing Counselors at Law Northeast Utilities Service Company i

City Place Post Office Box 270 i

Hartford, Connecticut 06103-3499 Hartford, Connecticut 06141-0270 W. D. Romberg, Vice President S. E. Scace, Vice President Nuclear Operations Services Millstone Nuclear Power Station Northeast Utilities Service Company Northeast Nuclear Energy Company Post Office Box 270 Post Office Box 128 Hartford, Connecticut 06141-0270 Waterford, Connecticut 06385 Kevin T. A. McCarthy, Director Regional Administrator Monitoring and Radiation Division Region I Department of Environmental Protection U.S. Nuclear Regulatory Commission 79 Elm Street 475 Allendale Road Post Office Box 5066 King of Prussia, Pennsylvania 19406 I

Hartford, Connecticut 06102-5066 Allan Johanson, Assistant Director Board of Selectmen Office of Policy and Management Town Office Building Policy Development and Planning Division Haddam, Connecticut 06438 80 Washington Street Hartford, Connecticut 06106 Resident Inspector l

Haddam Neck Plant J. P. Stetz, Vice President c/o U.S. Nuclear Regulatory Commission-Haddam Neck Plant 361 Injun Hollow Road Connecticut Yankee Atomic Power Company East Hampton, Connecticut 06424-3099 362 Injun Hollow Road East Hampton, Connecticut 06424-3099 Nicholas S. Reynolds Winston & Strawn D. J. Ray 1400 L Street, NW Haddam Neck Unit Director Washington, DC 20005-3502 Connecticut Yankee Atomic Power Company 362 Injun Hollow Road i

East Hampton, Connecticut 06424-3099 J. M. Solymossy, Director Nuclear Quality and Assessment Services Northeast Utilities Service Company Post Office Box 270 Hartford, Connecticut 06141-0270 k